I hereby give notice that an ordinary meeting of the Henderson-Massey Local Board will be held on:

 

Date:                      

Time:

Meeting Room:

Venue:

 

Thursday, 20 March 2014

3.30pm

Council Chamber
Henderson Civic Centre
6 Henderson Valley Road
Henderson

 

Henderson-Massey Local Board

 

OPEN AGENDA

 

 

 

MEMBERSHIP

 

Chairperson

Vanessa Neeson, JP

 

Deputy Chairperson

Shane Henderson

 

Members

Brenda Brady, JP

 

 

Peter Chan, JP

 

 

Warren Flaunty, QSM

 

 

Will Flavell

 

 

Tracy Kirkley

 

 

Luke Wilson

 

 

(Quorum 4 members)

 

 

 

Glenn Boyd

Relationship Manager

Local Board Services (West)

 

 

Busola Martins

Local Board Democracy Advisor

 

13 March 2014

 

Contact Telephone: (09) 839 3514

Email: busola.martins@aucklandcouncil.govt.nz

Website: www.aucklandcouncil.govt.nz

 

 


 

 

 


Henderson-Massey Local Board

20 March 2014

 

 

ITEM   TABLE OF CONTENTS                                                                                        PAGE

1          Welcome                                                                                                                         5

2          Apologies                                                                                                                        5

3          Declaration of Interest                                                                                                   5

4          Confirmation of Minutes                                                                                               5

5          Leave of Absence                                                                                                          5

6          Acknowledgements                                                                                                       5

7          Petitions                                                                                                                          5

8          Item withdrawn                                                                                                              5

9          Item withdrawn                                                                                                              5

10        Extraordinary Business                                                                                                5

11        Notices of Motion                                                                                                          6

12        Local economic development July to December 2013: Henderson-Massey Local Board                                                                                                                                         7

13        Auckland Transport Quarterly Update to Local Boards - For the quarter 1 October to 31 December 2013                                                                                                             15

14        Auckland Transport Update Report – Henderson-Massey Local Board              67

15        Local & Sports Parks West Draft 2014/2015 Capital Works Programme              83

16        Auckland Council Property Limited Local Board Six-Monthly Update
1 July to 31 December 2013                                                                                       
85

17        Infrastructure and Environmental Services Update Report                                 115

18        Appointment of additional members to Western Joint Funding Committee     137

19        Confirmation of Workshop Records                                                                       139

20        Henderson-Massey Local Board - Meeting Schedule

This report was not available at the time the agenda was compiled and will be tabled at the meeting.

21        Chair's report                                                                                                             147

22        Special Housing Areas: Tranche 3 - Confidential report (confidential report)

Reason for confidentiality: The public conduct of the part of the meeting would be likely to result in the disclosure of information for which good reason for withholding exists under section 7.

s7(2)(c)(ii) - The withholding of the information is necessary to protect information which is subject to an obligation of confidence or which any person has been or could be compelled to provide under the authority of any enactment, where the making available of the information would be likely to damage the public interest.

In particular, the report/presentation contains information which, if released, would potentially prejudice or disadvantage commercial activities.

23        Landowner approval for the Harbourview construction yard (confidential report)

Reason for confidentiality: The public conduct of the part of the meeting would be likely to result in the disclosure of information for which good reason for withholding exists under section 7.

s7(2)(b)(ii) - The withholding of the information is necessary to protect information where the making available of the information would be likely unreasonably to prejudice the commercial position of the person who supplied or who is the subject of the information.

In particular, the report contains monetary values that could be prejudicial to negotiations with AT or tenderer.

  24      Consideration of Extraordinary Items 

 

 


1          Welcome

 

2          Apologies

 

At the close of the agenda no apologies had been received.

 

3          Declaration of Interest

 

Members are reminded of the need to be vigilant to stand aside from decision making when a conflict arises between their role as a member and any private or other external interest they might have.

 

BOARD MEMBER

ORGANISATION

POSITION

Vanessa Neeson, JP (Chairman)

N/A

N/A

Shane Henderson (Deputy Chairman)

Waitakere Community Law Service
Ranui Action Project

Employee
Co-Chairman

Brenda Brady, JP

Keep Waitakere Beautiful
Safer West Community Trust
Sunnyvale Residents & Ratepayers Society Inc.
West Auckland Historical Society
District Licensing Committee

Trustee
Trustee
Member
Member
Member

 Peter Chan, JP

Cantonese Opera Society of NZ
Asian Leaders Forum
NZ-Hong Kong Business Ass.
NZ-China Business Ass.
Auckland Chinese Environment Protection Association (ACEPA)

Member
Member
Member
Member
Advisor

Warren Flaunty, QSM

Westgate Pharmacy
West Auckland Hospice
NorSGA Properties
Westgate Pharmacy Ltd
The Trusts Community Foundation Ltd Rodney Local Board
Waitemata District Health Board
Waitakere Licensing Trust
Massey Matters Inc.
Massey Birdwood Settlers Ass.
Taupaki Residents & Ratepayers Ass.

Contractor
Trustee
Director
Director
Director
Elected Member
Elected Member
Elected Member
Member
Member
Member

Will Flavell

Rutherford College

Employee

Tracy Kirkley

District Licensing Committee

Heart of Te Atatu South         

Member

Member

Luke Wilson

NZ Police - Massey Community Constable
D.A.R.E. West

Employee
Member

 


 

4          Confirmation of Minutes

 

That the Henderson-Massey Local Board:

a)         Confirms the minutes of its meeting, held on Thursday, 6 March 2014 as a true and correct record.

 

5          Leave of Absence

 

At the close of the agenda no requests for leave of absence had been received.

 

6          Acknowledgements

 

At the close of the agenda no requests for acknowledgements had been received.

 

7          Petitions

 

At the close of the agenda no requests to present petitions had been received.

 

8          Item withdrawn

 

 

9          Item withdrawn

 

 

10        Extraordinary Business

 

Section 46A(7) of the Local Government Official Information and Meetings Act 1987 (as amended) states:

 

“An item that is not on the agenda for a meeting may be dealt with at that meeting if-

 

(a)        The local authority by resolution so decides; and

 

(b)        The presiding member explains at the meeting, at a time when it is open to the public,-

 

(i)         The reason why the item is not on the agenda; and

 

(ii)        The reason why the discussion of the item cannot be delayed until a subsequent meeting.”

 

Section 46A(7A) of the Local Government Official Information and Meetings Act 1987 (as amended) states:

 

“Where an item is not on the agenda for a meeting,-

 

(a)        That item may be discussed at that meeting if-

 

(i)         That item is a minor matter relating to the general business of the local authority; and

 

(ii)        the presiding member explains at the beginning of the meeting, at a time when it is open to the public, that the item will be discussed at the meeting; but

 

(b)        no resolution, decision or recommendation may be made in respect of that item except to refer that item to a subsequent meeting of the local authority for further discussion.”

 

11        Notices of Motion

 

At the close of the agenda no requests for notices of motion had been received.

 


Henderson-Massey Local Board

20 March 2014

 

 

Local economic development July to December 2013: Henderson-Massey Local Board

 

File No.: CP2014/01835

 

  

Purpose

1.       This report provides an update for the Henderson-Massey Local Board on local economic development activities delivered by the Economic Development Department for the period July to December 2013.

Executive Summary

2.       The 2013/14 local economic development work programme in the Henderson-Massey Local Board area includes:

·        Preparation of an economic development overview presenting a range of indicators on the Henderson-Massey economy, issues and opportunities

·        The Business Improvement District (BID) Partnership programme in Te Atatu and support for the Henderson Central Retailers Association

·        Support for the roll out of ultrafast broadband and the sustainable and targeted provision of public WiFi.

3.          The proposed 2014/2015 work programme builds on existing activities.

 

Recommendations

That the Henderson-Massey Local Board:

a)   Receives the six-monthly update on local economic development activities from July to December 2013.

b)   Provides feedback on the proposed 2014/2015 local economic development work programme of:

i.        Economic analysis and planning for the local economy in Henderson-Massey.

ii.       Support for the Business Improvement District Partnership programme in Te Atatu and pre-BID establishment work in Henderson.

iii.      Support for the roll out of ultrafast broadband and the sustainable and targeted provision of public WiFi.

c)   Nominates Local Board Member(s) to attend the Business Improvement District Policy (2011) review workshops and represent the view of the Local Board.

 

Discussion

4.       Economic Development Department champions Auckland’s Economic Development Strategy (EDS), which aims to develop an economy that delivers opportunity and prosperity for all Aucklanders and New Zealand.  The department works with ATEED, business, Government and community stakeholders to lead local economic development, regional economic strategy and policy advice, economic analysis and advocacy, digital policy and international relations on behalf of Auckland Council.

5.       This report focuses on local economic development activities in the Henderson-Massey  Local Board area.  An overview of the regional economic work programme undertaken by the Economic Development Department and ATEED to implement the EDS is provided to the Economic Development Committee, and is made available for information to Local Boards.  

6.       Under the guidance of global city development expert Greg Clark, and with the assistance of representatives from business, the wider Auckland Council and Government, critical priorities for Auckland’s future economic performance have been identified.  These are to:

·        Establish a new Auckland Leadership Team

·        Raise youth employability.  At the local level this means:

increasing the number of opportunities for young people to gain work experience

·        Build, retain and attract talent. At the local level this means:

encouraging our businesses to invest in skills

thoroughly understanding Auckland’s skills shortages

·        Build the Auckland business proposition for a business-friendly city

·        Boost the investment rate into Auckland’s economy and infrastructure

·        Motivate greater investment in products, services and markets. At the local level this means:

promoting the benefits of innovation and entrepreneurship

creating and connecting spaces for innovation and entrepreneurship

·        Increase Auckland’s visibility internationally

·        Optimise Auckland’s platforms for growth: housing, transport and availability of employment land. At the local level this means:

developing and adopting a new implementation model to achieve growth in key locations – CBD and metropolitan centres

leveraging the fibre network to its full potential

·        Support improved performance of Māori businesses.  At the local level this means:

working to support Māori businesses to grow.

7.       We are planning a workshop with Local Board economic development portfolio holders, ATEED and the Economic Development Committee on making local economic development in Auckland more strategic, focused and united. Further information will be provided through the Local Board Advisors.

Economic Development Overview

8.       An economic development (ED) overview has been prepared for the Henderson-Massey Local Board area.  The overview outlines the current economic picture in Henderson-Massey, recent trends, and identifies particular strengths or points of difference the local board area has in comparison to the region wide picture. It is primarily a data driven view drawing on the statistics available covering a range of indicators including demographics, incomes and housing, education and skills, employment and occupation, sectoral strengths, business growth and development trends.

9.       The overview has been distributed to Local Board members, Council departments and BIDs.     It can be used as a key input to developing a Local ED Action Plan for Henderson-Massey should the Local Board allocate funds to develop a Local ED Action Plan. The information can also inform the Local Board Plan currently under development.

10.     In 2012, GDP in Henderson-Massey was $2.9 billion, which was 3.7 per cent of the Auckland regional GDP. Manufacturing and retail trade are the dominant sectors in the Henderson-Massey economy.

Henderson-Massey’s industrial mix by GDP (2012)

Source: Infometrics

 

11.     Stand out facts about Henderson-Massey from the ED overview include:

·        In terms of employment, the main sectors are those related to servicing the local population (such as education, health, residential care, local government) which is the second largest of all Local Board areas.

·        Residents are less likely to have a degree level qualification or higher and more likely to have no qualifications than the regional average.  The proportion of young people not in education employment or training is high.

·        Unemployment is higher and average household incomes are lower than the regional average.

·        Manufacturing remains the most important sector in terms of GDP with strengths in fruit, oil, cereal and other food product manufacturing, meat and meat product manufacturing and polymer product and rubber product manufacturing.

·        Henderson-Massey has strengths in a number of sectors in which Auckland competes internationally including construction and engineering, food and beverage, health technologies and niche manufacturing.

12.     Employment in Henderson-Massey increased by an average of 1.8 per cent pa in the ten years from 2002-12, similar to the Auckland growth rate of 1.9 per cent.  During this period, Henderson-Massey job numbers increased most in healthcare and social assistance (+1,570 jobs), public administration and safety (+900), education and training (+790), wholesale trade (+330), other services (+300) and construction (+290).

13.     The ED overview includes the following initial assessment of the strengths, challenges and opportunities within the local economy.

 

 

 

 

An assessment of Henderson-Massey’s economic potential

Strengths

Challenges

Diverse sectoral strengths

·      Strong employment base with employment across a range of sectors including several sectors in which Auckland competes internationally.

 

Major investments underway

·      Significant investments underway at Hobsonville / Westgate which have been prioritised in the Auckland Plan.

Education

·      Lower than the regional average in terms of educational attainment.

 

Meeting growing income generation needs

·      Lower than average household incomes

·      Meeting the demand for local employment opportunities as population increases.

Opportunities

Business friendly

·   Significant opportunities to attract employment to the area through developments at Westgate and Henderson.

Innovation and exports

·   Develop the innovation and export potential in key sectors in which Henderson-Massey has a competitive advantage including construction and engineering, food and beverage, health technologies and niche manufacturing.

Skills

·   Opportunities to access existing skills infrastructure and the West Auckland Youth Guarantee Network to improve education and skills attainment.

·   Strong community focus through Massey Matters, McLaren Park Henderson South Community Initiative and a range of other community initiatives can help improve skills and contribute to economic outcomes.

Vibrant and creative city

·   The developments at Westgate provide opportunities to develop a vibrant centre catering for locals and residents from neighbouring areas. 

·   Opportunity to examine how Henderson / Lincoln Road functions and meets the needs of the local population.

·   Further development of the film industry cluster in the area.

 

BID Partnership Programme

14.     The BID Partnership Programme approach is a public-private partnership between business associations that have a commitment to develop and promote their local business environment and Auckland Council.  In work to date since Auckland Council was established there has been a focus on sharing best practice and developing consistent governance, processes and practices across the region’s 46 BIDs.

15.     Each BID has signed a Partnering Agreement with Auckland Council.  These agreements define the relationship between Auckland Council and individual business associations operating as BIDs.  Several have also signed a discretionary Memorandum of Understanding with their Local Board. The MOU is an opportunity to agree mutual goals and objectives and to support each other’s programme of work where applicable. 

16.     BID Partnership Advisors hold monthly networking meetings for BID managers and interested business associations that focus on professional development and sharing information and best practice. Topics covered from July to December 2013 include:

·        Auckland Transport (importance of good parking in our centres)

·        AGM checklist and meeting procedures

·        ATEED local events

·        WiFi how to make the most of Apps

·        Overseas conferencesreport back and learnings from BID attendees

·        Signs and alcohol bylaws

·        Social enterprises

·        Using Marketview results for business attraction

·        Media awareness

·        Your Website how to review it and improve it

·        Using information from Local ED Overviews and opportunities to engage with Local ED Action Plans  

 

17.     A refresh of the Auckland Region Business Improvement District Policy (BID Policy 2011) will be undertaken in 2014. The proposed BID Policy will go before the Regional Strategy and Policy Committee for final approval in November 2014.

18.     The process to review the BID Policy will involve consultation with both business associations and Local Board representatives. Separate workshops will initially be held for the two stakeholder groups, followed by a combined workshop with both the business associations and Local Board representatives. Local Board representative(s) are sought for involvement in the review process.

19.     Any suggestions made at these workshops to amend the existing BID Policy (2011) will be brought before the Local Board for its consideration and feedback.

20.     There is much activity happening with the establishment of new BID areas (including State Highway 16 and Devonport, who will be balloting in March 2014). Several other locations are actively working with the BID team on preparatory work towards establishment. Existing BIDs undertaking expansion ballots prior to June 2014 include Otahuhu and Manukau Central.

21.     Twenty-seven existing BIDs have chosen to increase their amount of target rate for the 2014/2015 financial year. Every one of these proposed increases has followed the process of advising all members and receiving approval of the proposed new amount from members at Annual General Meetings.

Te Atatu Peninsula BID

22.     The Te Atatu Peninsula Business Association held their AGM on 11 September 2013 with a good turnout and a presentation from the group organising the 2014 Harbourview Sculptural Trail. The BID Manager provided a review of past activities and presented the Te Atatu Peninsula Strategic Plan. The members ratified and adopted the strategic plan with enthusiasm looking forward to the next year’s progress. The members also ratified and adopted the BID target rate for 2014/2015 which remains at $82,000 per annum.

23.     The Te Atatu Peninsula BID Manager has been working hard since coming permanently onboard and has started to implement actions from the strategic plan. Actions include a review of the Te Atatu Views community newsletter, budget and costings plus refocusing events and promotions to provide benefit to the local businesses, and a business retention and attraction programme.

24.     The Te Atatu Views magazine is now quarterly, full colour, bigger in size and volume and delivered within budget. Feedback has been fantastic from both the businesses advertising and the community.

25.     The BID Manager has developed good relationships with the members and business involvement in promotions and events is increasing.

26.     Work has commenced in the new Te Atatu Peninsula Library and Community Centre, which is certain to be a draw for the town centre and focal point for promotions and events.

Henderson Central Retailers Association Inc

27.     The Henderson-Massey Local Board has provided funding for the BID team, in association with the Henderson Central Retailers Business Association and ATEED West, to undertake a pre-BID fact finding survey. This work will identify the issues, concerns and opportunities facing Henderson business owners. The survey would include businesses located in the Henderson Central/South and Henderson Valley area.

28.     A working party has been formed including representation from Henderson-Massey Local Board, Henderson Central Retailers Business Association, ATEED West, and Henderson property owners and business owners.

29.     A business database containing over 800 business entities has been purchased and the survey questions and documents are currently being developed. The survey is scheduled to begin in early March 2014 with a report scheduled for presentation to the Henderson Massey Local Board in May 2014.

30.     The objective of the Henderson pre-BID fact finding survey is to establish if there are some galvanising issues/opportunities that bring together businesses in the area, supportive of being part of a business network or association. The information collected in the survey will provide evidence of support to continue on to establish a Henderson BID Partnership Programme starting July 2015.

Ultrafast Broadband

31.     The third year of the rollout of Ultrafast broadband (UFB) ends on 30 June 2014.  The rollout is a third of the way through the nine year programme. So far over 60,000 premises region wide can connect to UFB with just over 11per cent of these premises connected. This is in line with the rate of uptake predicted at the start of the UFB rollout. 

32.     Chorus intends to provide updates to Local Boards on the progress of the rollout in each area and Council officers will work with Local Board services to arrange times in the appropriate Local Board Workshops as the updates become available.

 

Public WiFi

33.     Public Wi-Fi is available in all 56 libraries and in 23 public open spaces around Auckland.  In January 2014 the Libraries WiFi service was used 173,000 times by 110,000 people totalling 7.7 million minutes of free Wi-Fi usage.  The public open space service has been experiencing network stability issues and this has limited usage.  These issues are now resolved and we expect to see usage grow in line with Libraries usage.  The public open space service was used 49,631 times by 44,419 people totalling 893,494 minutes of free WiFi usage.

 

Work programme 2014/2015

34.     The proposed 2014/2015 local economic development work programme in the Henderson-Massey Local Board area is set out below.

 

OPEX Project description

Economic analysis and planning on the local economy in Henderson-Massey.

BID Partnership programme in TeAtatu and pre-BID establishment work in Henderson.

Support for the roll out of ultrafast broadband and the sustainable and targeted provision of public WiFi.

Consideration

Local Board Views

35.     This report informs the Henderson-Massey Local Board on progress implementing the agreed local economic development work programme.  Feedback from the Board is welcome to shape ongoing activities.  

Maori Impact Statement

36.     Matters relating to Māori wellbeing are addressed as part of specific projects and are reported in the relevant Board and committee reports.

General

37.     N/A.

Implementation Issues

38.     There are no implementation issues.

 

Attachments

There are no attachments for this report.     

Signatories

Authors

Trudi Fava - Strategic Planner

Authorisers

Janet Schofield - Business Area Planning Manager

Glenn Boyd - Relationship Manager Henderson-Massey, Waitakere Ranges, Whau

 


Henderson-Massey Local Board

20 March 2014

 

 

Auckland Transport Quarterly Update to Local Boards - For the quarter 1 October to 31 December 2013

 

File No.: CP2014/04271

 

  

 

Purpose

1.  The purpose of this report is to inform local boards about progress on activities undertaken by Auckland Transport (AT) in the three months October - December 2013, and the planned activities anticipated to be undertaken in the three months January – March 2014.

 

 

Recommendation/s

That the Henderson-Massey Local Board:

a)      Receives the Auckland Transport quarterly report.

 

 

Discussion

Main activities during the period under review

 

Investment and Development

 

City Rail Link

2.       The Independent Commissioners’ recommendations in relation to  Auckland Transport’s  Notice of Requirement for the designation to construct and operate the City Rail Link, is now expected by the end of February 2014. An Engineering/ Architectural consortium led by Aurecon, has been awarded the contract for the role of  Principal Technical Advisor Tender for the ongoing technical support of the project. Its initial focus will be on the development of the  Reference Design to support a subsequent stage of delivery preparation. This team will be collocated with Auckland Transport’s project team in an integrated project office by March.

EMU Depot

On Budget and Practical Completion issued, CAF and Transdev now occupying

 

EMU Procurement

3.       Seven three-car units are now in Auckland, with the first four of these undergoing mainline testing between Wiri and Newmarket and also on the Onehunga branch line. Driver training is scheduled to begin in late February and will utilise two units. Units number 8 and 9 will leave Spain at the end of January and are due in Auckland early March.  Train delivery and commissioning is currently occurring to programme.

Road Design & Development

 

St Luke's Intersection

4.       Provision of increased walking and cycling, extended bus lane and additional right turn lane for Great North Road to St Lukes Road. Tender submissions to NZTA for physical works are being evaluated. It is expected that the contract will be awarded by mid-February.

 


Waterview Cycle Way connection

5.       The Waterview Walking and Cycling project is required as a condition of the decision of the Waterview Connection. The Unitec Board approved new development strategy for Precinct. Consultation with Ngati Whatua to restart based on alternative route. Draft SAR has been received that proposes a preferred route. This will allow property purchase to proceed. Public engagement will commence in March 2014.

 

New Lynn to Waterview Scheme Cycle Way

6.       Provision of a shared cycling and walking route between Soljak Place and the New Lynn town centre. Scheme Assessment tender closed Dec 2013. Tender evaluation and award Jan 2014.

 

Taharoto/Wairau - Stage 3

7.       Negotiations are continuing with Atlas regarding land acquisition.  An interim solution to provide continuity of walking and cycling facilities has been constructed as part of Stages 6 & 8.

 

North Area Bus Improvement Progrogramme – Onewa Road

8.       Funding application is almost complete.  A workshop to update the Local Board is scheduled for February.

Devonport Marine Square

9.       Upgrade the Devonport Marine Square, provide improved connection from the ferry building to the town centre and enhance the transport hub. Construction will start in February 2014.

 

King/Queen/Constable Intersection Upgrade

10.     Construction contract has been awarded to Transfield Services. Programmed commencement date on site is 20th January 2014.

 

The Redoubt Road - Mill Road

11.     The Redoubt Road - Mill Road corridor provides an arterial road connection east of State High 1 between Manukau, Papakura and Drury and includes Murphys Road from Redoubt Road to Flatbush School Road.

1, Scheme Assessment is being finalised

2, Preparation for Notice of Requirements documentations for lodgement during second quarter 2014 is underway.

3, On-going consultation with iwi, residents and interest groups

4, Funding request from NZTA and procurement activities for the investigation of Phase 2 now initiated. 

 

Lincoln Road - Corridor Improvements

12.     The project involves widening Lincoln Rd between Te Pai Place and Motorway Interchange to accommodate additional transit/bus lanes on both sides. Public submissions on the proposed design will be continuing till February 2014. Works associated with the notice of requirements will be also starting in February.

 

Te Atatu Road : Corridor Improvements

13.     Road Corridor Improvement project on Te Atatu Rd from School Rd/Edmonton Rd intersection to SH16, works include rood corridor widening by 2.88m each side. August 2014 is the new forecast starting date for physical works due to delay in land take. More than 85% of the required land has been purchased and planned to complete the land purchase by April 2014. Building consent application to be lodged by March 2014.

 

 

Park and Ride Silverdale-Stage 2

14.     The resource consent application for the land use consent has been resubmitted and will be partially notified to the adjacent property owners.

 

Whangaparaoa Road four Laning

15.     The project has been put on hold until the AT Board makes a decision on Penlink, possibly in February 2014.

 

Orpheus Drive Shared Path Cycle Way

16.     Awaiting business case sign off. Tender for SAR being prepared.

 

Tamaki Drive and Ngapipi Intersection Safety Improvements

17.     The Tamaki, Ngapipi intersection is uncontrolled and an accident black spot. This projects seeks to address the safety issues by providing a controlled intersection treatment. In addition, the intersection will be future-proofed by extending the seawalls in the vicinity so that the future aspirations for Tamaki Drive are enabled.

 

Warkworth SH1 intersection improvement

18.     NZTA have completed  the design of the walking and cycling facilities between Hill St and Hudson Rd.  This work will be undertaken by June 2014  as a variation to the Hudson Rd contract.  SKM are remodelling the Hill St intersection taking into account RONS Puhoi to Warkworth and the Unitary Plan growth assumptions.

 

Albany Highway (Sunset to SH18)

19.     Reviewing NZTA proposals for the SH1/18 connection and the impact on Albany Highway South traffic volumes.  The purpose of this review is to ensure that AT has sized the road correctly and the NZTA work has a potential to increase traffic volumes along the route.

 

Brigham Creek Road Corridor Improvements

20.     The scoping phase is expected to be completed in February 2014.  The following activities are planned between Jan and Mar 2014:

* Summary and prioritisation of issues to be investigated under the feasibility phase.

* Production and review of final scoping report.

* Commence procurement of resources for the feasibility phase.

 

Beach Road Cycle Route

21.     Detailed Design Tender going out to market 24/03/2014. Detailed design to be complete 30/06/2014. Delivery of AT connecting sections, from Churchill St. to Mahuhu Cres, to be aligned with NZTA Grafton Gully Cycleway delivery in Sept 2014. The entire project (Beach Rd. to Quay St.) scheduled for completion Dec 2014.

 

Quay Street - City Centre Master Plan

22.     The project is currently looking at options for the seismic upgrade of the seawall between Princes and Marsden wharves. The work is due to be complete by the end of June 2014 after which a preferred option will be selected with a view to starting construction in early 2015.

 


Newmarket Level Crossing

23.     Replace Level crossing in Newmarket that constrains train movements into/out of Newmarket Station and inhibits planned increases in timetable frequencies. The AT Board has confirmed the crossing will be at Cowie Street. Engagement with stakeholders and preparation of design documentation is progressing.

 

New Lynn to Waterview Scheme Cycle Way

24.     Scheme Assessment tender closed Dec 2013. Tender evaluation and award Jan 2014.

 

Tiverton-Wolverton Stage 2

25.     Complete remaining 100m section of pavement reconstruction work on Tiverton Road and all pavement reconstruction works on New Windsor Road following completion of retaining wall construction. New Windsor Road and overall project finishing works will be complete by end April 2014.

 

Key Agency Initiatives

 

Dominion Road Corridor Upgrade

26.     Design work underway

NORSGA

27.     Submissions have closed for Northside Drive East. Notice of Requirement and Public Hearing to occur March/April. Rua Road South under construction. Don  Buck Road extension works currently being tendered and construction to commence in March.

 

NORSGA PC 13 Hobsonvillle Point

28.     Working with Hobsonville Land Co and Auckland Council Property to secure site for permanent park and ride.

 

NORSGA PC14 Hobsonville Village

29.     Working group established with NZTA to jointly develop solutions to future congestion at Brigham Creek Road interchange and other strategic Connections.

 

Long Bay Glenvar Ridge Road

30.     An application for consent to undertake geotechnical investigations has been submitted to Auckland Council.  The NoR is under preparation and the preliminary design is progressing.  Further consultation with Iwi is being undertaken.

 

Penlink Toll Road

31.     Decision on the progression of Penlink is required by the AT Board and anticipated for end February 2014.

 

32.     Work to update the designation and consents for Penlink is progressing in lieu of this decision, and an RFP has been tendered with award programmed for end January 2014.

 

33.     As part of this work, additional communication with stakeholders and the local board will take place.

 

34.     AMETI –Package 4 – Pakuranga, Ti Rakau-Reeves Road (Provision of a busway between Pakuranga and Botany)

The scheme assessment is complete. Work is now commencing on the design and consenting phase of this project.

 

35.     AMETI - Package 2 Sylvia Park Bus Lanes

Design is complete and consent documentation is being prepared. The project team is working to secure property required for the proposed scheme.

           

36.     AMETI - Package 6  Mt Wellington (Improving connections to the west of the AMETI area.)

The Package 6 investigation is complete. It identified several components across the region for which detailed investigation is recommended as the next step. Some of these will be included within the AMETI programme.

 

37.     AMETI - Package 1 - Panmure Phase 2

This phase encompasses the replacement of existing Panmure roundabout with a signalised intersection. Construction of a two lane busway on the northern part of Lagoon Drive and a shared path for pedestrians and cyclists along the north side of Lagoon Drive from Queens Road / Jellicoe Road to the new Panmure Bridge.  The base design is complete. The design will be updated to align with the requirements of the proposed Auckland unitary plan and to ensure effects (e.g. on cultural heritage sites) are appropriately mitigated. Work is commencing on the consenting phase.

 

East West Link

38.     The primary objective of the project is to provide an improved freight connection between SH20/Onehunga and the Southdown (MetroPort) and adjoining SH1 inland port. The nature and scale of the access improvements allows construction to commence by 2016/2017 with forecast completion by 2019/2020.

 

Public Transport Development

 

Mt Albert Train Station Upgrade Stage II

39.     Design phase to cover platform stairs and upgrade underpass, underway.

 

Ferry Terminal Upgrade – Bayswater

40.     Marine works (dredging and pontoon) consented and ready to go to construction. Funding application for land based design works is in progress.

 

Pukekohe Station Upgrade

41.     Concept design for the proposed station layout is under review based on long term plan for electrification of  Papatoetoe to Pukekohe rail station. Concept should be finalised / signed off by April 2014.

 

Half Moon Bay Ferry Terminal

42.     This projects entails upgrade of the Half Moon Bay Ferry Terminal to address the safety issues on water and land, improvements of parking facilities, traffic circulation and amenity. Still awaiting sign off for permanent parking changes. Delay was incurred  at request for additional disabled parking spaces.   Staging of the main project concept plan proposals is on-going. Early staging to focus primarily on PT.

 

Otahuhu Bus-Train Interchange

43.     To upgrade Otahuhu Train Station to a Bus-train interchange and park and ride to enable implementation of the new propose public transport network plan.The tender for detailed design closed on 17 January 2014 and is currently being evaluated.  This remains an extremely tight programme but is on track for construction completion in 1st half of 2015.

 

Manukau Bus Interchange

44.     Design tender documentation is being prepared. Funding approval has been given for the design phase and tenders will be out to the market early February 2014.

 

Puhinui Station Upgrade

45.     Initial concept investigation underway. Targeting June 2014 for completion of design work

 

Rail Platform Extensions

46.     Extending the platforms of 11 stations 5-15m each to bring them into line with other platforms on the network. First three stations with platform extensions are now nearing completion. Good progress is being made on the next 4 stations. Project Manager has accelerated works to complete all extensions by June 2014.

 

Downtown Ferry Terminal Pier 2 Upgrade

47.     Scope of work is being worked through with PT Operations. New covered waiting area will be installed in pier 2 by end of April 2014

 

Downtown Ferry Terminal Pier 3 & 4 Upgrade

48.     Scoping and initiation works under development is coordination with the Harbour Edge Programme

 

Parnell Train Station

49.     Detailed design tender to be issued.

 

New Lynn Rail Station Electronic Gates

50.     Concept designs being finalised and order for gates placed. 10 month lead time for gates and design for gates coverage and balustrade to be finalised over this period, followed by construction of kiosk and supporting works for gateline.

 

Re-development Devonport Wharf

51.     Significant work is happening on the Devonport Wharf.  Auckland Council and Auckland Transport are working together to improve structural works on Victoria Wharf and improve the Boardwalks and retail space.

 

Panmure Rail/Bus Interchange (AMETI Phase 1)

52.     Panmure Bus Interchange (AMETI Phase 1) handover from contractors took place 24 December 2013, with the official opening on18 January 2014.  Services have been rescheduled so that from this date, Howick & Eastern and NZ Bus services will travel via the new interchange.

 

New bus network in South Auckland

53.     Final decisions on bus routes for the new network in South Auckland were announced on 9 December 2013 and communicated to stakeholders, with a significant number of changes to proposed routes made as a result of customer feedback.

 

Bus Services - Integrated Ticketing & fares

54.     The implementation of Auckland Integrated Fare System (AIFS) “HOP” on buses, resumed after intermittent technical issues were resolved in September 2013, with roll-out on all NZ Bus services taking place 13 October - 8 December 2013.  This included North Star, Metrolink, LINK, Go West and Waka Pacific services.  AT staff were on the road at key locations to support drivers and customers.  The implementation schedule for AIFS/HOP with remaining bus operators is as follows: January 2014 – Bayes Coachlines school buses; February 2014 – Ritchies, Howick & Eastern; March 2014 – Waiheke Bus Company, Tranzit, Party Bus Company school buses. Negotiations re implementation date for two further minor operators are ongoing (Airbus and Murphy Buses school buses).

 

Ferry Services - Integrated Ticketing & fares

55.     It is intended to phase out the 10 trip tickets from 17 February 2014 in favour of AT HOP card Stored Value pricing (the same as 10 trip ticket pricing). AT is developing an AT HOP Monthly Pass for ferry users.  Implementation timeframe TBC. Note:- Devonport and Stanley Bay will be phased out later by Fullers

Strategy and Planning

 

Auckland Integrated Transport Programme (ITPv2) and its key components

56.     Work is progressing on the development of the next version of the ITP which is due by the middle of 2014.  Work are also continuing on the development/updating of the key components of the ITP including:

57.     Regional Rapid Transit Review (RTN) review – further analysis is being undertaken as required in view of the RDS update

Rail Development Strategy (RDS) update – in progress

Rail Level Crossings Study – joint review with KiwiRail in progress

Park and Ride and Parking Strategy – draft strategy was presented to the AT Board in December.  The Board has required consultation of the draft strategy.

Regional Passenger Transport Plan – formally adopted by the AT Board on 23rd September 2013.  Consultation of the new network for the other areas in Auckland will be undertaken in 2014-15.  Implementation of the new network will commence in early 2015.

Regulatory planning

58.     Strategy and Planning continues to lead and co-ordinate AT’s responses to proposed plan changes and Notices of Requirements (NoRs) to ensure that land use and transport are integrated and that proposed land use changes enable AT to deliver its capital works programme.  During the second quarter, there are 26 applications that are in progress.  There were no new applications made this quarter.

59.     AT also continued working closely with the Auckland Council on the review of the notified Unitary Plan.  A series of internal workshops were conducted within AT during this quarter.  AT’s feedback on the notified plan is currently being consolidated and Strategy and Planning is liaising with the council on inclusion of feedback as part of the council’s submission.

60.     AT has also initiated a review of the application lodged by the Further North Alliance (on behalf of NZTA) with the Environmental Protection Agency (EPA) for a number of resource consents and a Notice of Requirement for the proposed Puhoi to Warkworth motorway project.

Corridor management plans (CMPs)

61.     The nine priority arterial CMPs in the 2012/13 year have now been completed:

Great North Road-Rata St-Ash St corridor

Albany Highway-Greville Rd-Tawa Dr corridor

Takapuna North (East Coast Road Stage 2)

East Tamaki Road-Springs Rd-Harris Rd corridor

City East West Transport Study

Tamaki Drive-Ngapipi Rd-Kohimarama Rd-Kepa Rd corridor

Ellerslie-Panmure Highway

Balmoral Road-St Lukes Road corridor

Great South Road Stage 2

Funding Implementation Plans (FIPs) for the programmes proposed in each of the completed CMPs are currently being prepared, with the prioritised projects to be included in the future ITP programme.

Nine CMPs under the 2013/14 CMP programme are currently being developed:

Oteha Valley Road (Albany Expressway to East Coast Road) – study underway, initial consultations with the Upper Harbour Local Board and the Albany Village Business Association were undertaken this quarter

Great North Road (between Ash Street and Karangahape Road) – study underway, initial consultation with Waitemata Local Board undertaken in December

New North Road (Blockhouse Bay Road to Mt Eden Road) – study commenced in January

Manukau Road (Broadway to Royal Oak roundabout) – study commenced in January

Onewa Road (SH1 Interchange to Verran’s Corner) – scoping underway, study to commence over the next quarter

Mt Albert Road – Carrington Road (Royal Oak roundabout to Great North Road) – scoping underway, study to commence over the next quarter

Green Lane East - West (Remuera Road to Balmoral Road) – scoping underway, study to commence over the next quarter

Brigham Creek Road – study underway in conjunction with Investigation and Design team

Pakuranga Road – study underway in conjunction with AMETI team

 

62.     The City Centre East-West (CEWT) Study has been completed.  Programmes put forward in the study relating to public transport facilities are now at the concept design stage, and are being co-ordinated with other city centre projects:

Downtown bus interchange

Wynyard Quarter bus interchange

Learning Quarter bus interchange

Fanshawe St urban busway

Wellesley St Civic upgrade

 

63.     Other studies being undertaken are as follows:

SH16 Te Atatu Rd Bus Interchange Preliminary Engineering Assessment – completed this quarter.  Next steps include the development of a business case to support the decision-making process, completion of the Te Atatu Bus Interchange feasibility study and work with NZTA to future proof the SH16 upgrades

64.     SH16 Bus Corridor Feasibility Study – study commenced this quarter to assess the feasibility of various bus facilities on SH16, to complement current works as part of the Western Ring Route project (which covers the section from Waterview to Westgate).  This study will look at the bus corridor from Waterview to the City Centre.

Transport modelling

65.     Work is continuing on the update/development of transport models including:

The CRL modelling programme development

The Auckland Passenger Transport (APT3) model update

Other projects such as for the Fanshawe St BRT, Te Atatu Road and Lincoln Road TMP, convention Centre, Rapid Transit Network (RTN) and the ITPv2

Asset Management Plan 2015-2018

66.     The development of the next Asset Management Plan 2015-2018 is continuing.  Consultations with Business Units are underway and linkages with the ITP are being developed.

Seismic Screening Programme

67.     Work is continuing on the screening of all transport assets for earthquake susceptibility. 

Asset Condition Surveys

68.     Work on the survey for higher risk transport assets has continued this quarter and completed at the end of December as programmed.  Minor safety and other issues are prioritised and addressed through the maintenance teams.  The more extensive defects are included in the long-term forward renewal works programme and, where feasible, coordinated with the capital works programme.

Community Transport

 

School Transport Programme and Road Safety Education

69.     The number of schools signed onto the TravelWise Programme has now reached 375.

70.     Key activities that were undertaken with the schools included, safety at the school gate parking enforcement, speed enforcement campaigns undertaken with the NZ Police, cycle training, scooter training, school leadership programme for intermediate and high school students and school curriculum transport related activities targeted at road safety and school travel options.

71.     Walking School Buses now number 359 in the region with a continued programme of recruitment and recognition for the volunteers who accompany the buses. 

72.     Demand for cycle training is still strong from schools and greater partnerships with the NZ Police, Sports Trusts and Bike NZ have been developed to deliver cycle training and cycle safety.

73.     The following regional road safety education campaigns are being delivered over the for the coming six months: 

Red light running campaign – focused at all road users

Pedestrian safety campaign – focused on youth and at risk sites

Cycle safety- focused on training, maintenance and share the road

Back to school speed campaign  - focused on targeting drivers speed around schools

 

Travel Planning and Cycle and Walking

74.     Commute travel planning packages and personal journey plans being delivered across the region targeting business, communities, business associations and tertiary institutions.

75.     The summer “Cycling’s the go” safety and promotional campaign is being delivered over the coming months targeting, cycle training, safety, guided rides and maintenance programmes.

76.     The development of the Auckland Cycle network continues with priority being placed on working with the NZTA on Grafton Gully and Waterview, working with Local Board Greenway proposals, Beach Road, Great South Road, Puhinui Road and the New Zealand Cycle Trail network expansion programme of the Airport to City route.

 

Road Corridor Maintenance

 

West

77.     The new road maintenance contract is “bedding in” and providing good operational and customer services within the Henderson – Massey, Waitakere and Whau local board areas. The inclusion of additional berm and vegetation management items since the issuing of the last report was supplied and exceptional growth conditions regionally, had bogged down the reactive capability of the contractor in the last 2 months of 2013. A change in methodology has been developed between Contractor and RCM management which will make treatment and information supply easier going forward. Unfortunately some additional cost implications as a result of these changes will affect overall budget allocations. Cost and activity reductions will have to be implemented in other areas for the remaining 2013 – 14 programs. Additional funding will be sourced during budget calculations for the next financial year.

78.     Progress in the large pavement reconstruction works and footpath renewal are on target throughout the western area. Pavement rehabilitation works have been or are nearing completion in Margan Ave, Kinross St, Henderson Valley Rd and View Rd. Projects that are continuing into 2014 and a list of forward works for your reference, that will soon be underway in the western network are - Birdwood Rd, Nikau St, Kervil Ave, Rimu St, Blockhouse Bay Rd and Titirangi Rd .

79.     Programming, investigation and design works are well underway for the sites allocated for 2014 – 15 program with future works in the design area targeting network sites beyond 2016 where possible.

80.     The extensive resurfacing program is also underway throughout the central – west region. To date 5.5km of asphalt surfacing has been completed to December. The schedule of activities includes approx. 12.5km of Asphaltic Concrete surfacing and 35km of various Chip Sealing (resealing) sites. This program continues on from the previous 3 years, due to recent bitumen price increases and site pre-sealing repairs costing more than expected, the total quantities have had to be reduced to match the budget allowance. 

81.     The slip repairs have been undertaken in the 5 sites Titirangi Road and Titirangi Beach Roads noted in the last report. Major retaining structures and road strengthening have been completed in Candia Road and Laingholm Drive. Final detailed design and both building & resource consents are in hand for a major slip repair site on Titirangi Road.

82.     Investigation of any opportunities to “future proof” the western network against storm and flooding impacts continues to be high priority, but funding through NZTA is unfortunately difficult to obtain for these works.

 

Streetlights

83.     Completed the section of Tamaki Drive (Okahu section) with new poles and luminaires in accordance with the Tamaki Drive approved upgrade report. There are only 25 poles and lights to complete the upgrade between Ngapipi Road and The Strand.

84.     St George Street Papatoetoe is currently being upgraded with new poles and lights.  The former decorative type lights will become gas look alike lights for decorative purpose only.

85.     Bowen Street in the CBD has been upgraded to provide increased safety for pedestrians walking into the city especially from the university at night.

86.     Installation of new lights and poles supporting the Vector undergrounding programme removing overhead lines. Areas where undergrounding has taken place are Epsom, and Penrose.

 

South

87.     The 2013/14 resurfacing programme ($15.3M) commenced during the period. All Chipseal sites are expected to be completed by early April and the Asphaltic Concrete sites by end of May 2014.

88.     The 2013/14 Pavement Rehabilitation and Reconstruction programmes are well underway. A large number of the sites were either completed or commenced during the period. Some of the completed sites include, Princess St Otahuhu, Te Irirangi Drive - Smales to Accent, Great South Road – Grande View to Corin and Ronwood to Gladding, Mahia Road – Coxhead to Hobart, Hill Road – Hill to Grande Vue, Hunua Gorge, and Pukeoware Road rehabilitation.

89.     The preseal repair, footpath and kerb/channel programmes of work are underway. The Contractors main focus during the period was to complete the works associated with the 2013/14 resurfacing and pavement rehabilitation sites.


Central

90.     Following months of planning between Auckland Council Stormwater, Watercare and RCM, a major upgrade of Carlton Gore Rd, between Davis Crs and George St, has commenced. The objective of this 6 month project is to upgrade the public stormwater system, separate the existing combined sewer system to prevent on-going sewer overflow discharges to the New Market Stream and to reconstruct the deteriorated road pavement. The three members of the Auckland Council Family have engaged Downer to undertake all components of the work to ensure disruption to the local businesses and residents is minimised and to achieve value for money for ratepayers.

91.     The pavement rehabilitation of Woodward Rd, between New North Rd and Carrington Rd, has been completed. This work was completed in collaboration with Kiwi Rail during a weekend shut down for the electrification of the Western rail line to minimise disruption to public transport users.

92.     After a major internal and external stakeholder management consultation period between RCM, RCA, PT and Downer,  approximately 11000 square metres of Jervois Road, between Ponsonby Road and Clarence Street were resurfaced over Labour Weekend.

 

93.     Spring growth has made berm mowing an area of focus for the Central team.

94.     Following consultations with local Iwi and the New Zealand Historical places trust, The Orakei Road (Shore to Ngapipi roads) road Rehabilitation Project is now underway.Completion is programmed for early March 2014.

95.     Negotiations between ATs maintenance contractors and the UFB Project contractors have now concluded. These negotiations which were driven by the Central AT Team have opened the way for ATs footpath contractors to upgrade footpaths and install UFB simultaneously.

 

Hauraki Gulf Islands

 

96.     Wharf Road Rehab stage one was completed in December with stage two from Muratai to Homai commencing in February.

CT Footpath – Tui Street completed in December

Wharf Road board walk completed in December

Waiheke Island reseals, 7.5 kms were completed in November

Pavement designs for Sea View Road rehab completed with work to commence February.

 

North

 

Rural North

97.     The focus during the December period was on giving the town centres a ‘spring clean’ before the Christmas period.   The work has progressed well with all townships 100% complete.   With many visitors expected to holiday at the spectacular beach locations in Rodney the coastal unsealed roads (e.g. Pakiri Road and Takatu Road) were given a maintenance run to ensure they are in top condition.

98.     In the North Rural the AWPT programme is progressing well with 1.5 kms completed in December.   To date the AWPT programme is 62% complete (by length).   Cost savings have also been delivered to Auckland Transport with the current spend approximately 10% below the target value.   The reseals programme has been slightly delayed with rain in December and is 56% complete, year to date.   The programme has been updated with the reseals now scheduled to be 100% complete by March.

99.     The Opex and Renewals rolling quarter and year to date budgets are on track.   The overall year to date variance against forecast is less than 1%.

 

Urban North

100.   Despite being a short month December has had some large and technical works completed within.The Fulton Hogan chipseal reseal program commenced in December and is expected to be complete late March.

101.   The Asphalt resurfacing is 85% complete and the target date for completion is late March early April with the aim of targeting additional monies should they become available.

102.   Rehabs in the North are progressing well with .576 km completed to the end of December however Hugh Green Drive is only 85% completed and has not made the completed works figures for December. The outstanding works for Hugh Green is the asphalt resurfacing which is planned to be tied in with roundabout construction at Spencer Rd.

103.   Kaipatiki Road Subsoils are complete and work has started on Bentley Road.

104.   Colonial Road work due to start at the end of January.

105.   There were no health and safety issues for the Fulton Hogan team in the month of December.

 

Road Corridor Operations

 

One Network

106.   The next step in the integrated road classification system project  - ‘collate all feedback and update the ONRC Framework;’ is ongoing this quarter.

107.   AT is currently progressing various Engineering Plan Approvals (EPA) for different packages of work for Waterview and other NZTA SH16 corridor improvements.

108.   AT has also been working with NZTA on SH16 Initiatives to reduce the impact of the on-going works to travel times, particularly for buses.  A package of quick win measures has been implemented to provide improved journey times for buses to mitigate the loss of key bus priority infrastructure. Measures include the reinstatement of, or new shoulder bus lanes, priority lanes on the motorway ramps and local road network.  NZTA has ensured coordination between the various projects along SH16, with particular regard to traffic management measures and timing of works to minimise the impact on travel times along the SH16 corridor.  Measures for the medium to longer term have been identified and these are currently at various stages of assessment.

 

Route Optimisation

109.   Stage 1 Investigation and traffic signal optimistaion completed on:

 

Quay Street

Lower Hobson St

Solent St

Customs Street

Lower Hobson St

The Strand

Victoria Street

Hobson

Stanley St

Wellesley Street

Hobson

Grafton Rd

The Strand

Quay St

Alten Rd

Albert Street

Quay St

Wellesley

Queen Street

Quay St

Newton Rd

 


 

110.   Stage 1 Investigation completed on

 

Mayoral Drive/Cook Street

Wellesley St W

Wellseley St E

Nelson Street

SH1

Fanshawe St

Hobson Street

Quay St

SH1

Karangahape Road

Ponsonby Road

Grafton Rd

Wellington Union

Franklin

Karangahape Road

Symonds Street

Mt Eden

Customs

Grafton Road

Khyber Pass

Symonds St

 

111.   Note Symonds Street revisited for consistency with CBD approach.

 

112.   Physical Works Programme (other routes across the region):

8 projects are at the scheme design stage

4 projects are at the detailed design stage

1 construction project is completed

 

Road Safety

 

Urban KiwiRAP risk mapping project

113.   Risk Mapping software has been completed. AT network corridors and intersections have been prioritised. Urban KiwiRAP coding and star rating work will commence shortly. The procurement plan has been approved and a tender will be let in February 2014.

 

Red Light Cameras

114.   NZ Police is currently managing a tender process for new safety camera equipment, which encompasses modern technology with up-to-date radar detection methods and wireless data download capability that will contribute to increased road safety benefits. This process will include investigating the benefits of dual purpose red light/speed cameras. Research demonstrates increased safety benefits from multi-purpose cameras able to detect and deter high-risk behaviours such as accelerating through intersections to beat red lights.

Parking and Enforcement

Waitemata

115.   Newmarket – Consultation commenced on a proposal to remove time limits from paid parking areas in Newmarket and move towards a demand responsive pricing approach similar to the Central City Parking Zone.  

 

116.   Beaumont Street, CBD - New area of paid parking on Beaumont Street opposite Victoria Park to improve parking availability for customers

 

117.   Sale Street and Halsey Street, CBD - New car share parking restriction bringing the total number of spaces to eight.

 

118.   Tuarangi Road, Grey Lynn - Conversion of the angle parking to parallel parking  on the southern kerb  of Tuarangi Road Grey Lynn at its junction with Great North Road. This improves safety and removes the danger of vehicles reversing into the live traffic lane.

 

119.   Turner Street, CBD - New area of paid parking to replace redundant vehicle crossing.

Waiheke

120.   Matiatia – Some 117 parking spaces at Matiatia were converted from underutilized lease parking to pay and display in November to free up short term parking for people wishing to catch a ferry to Auckland.

Orakei

121.   Mission Bay, St Heliers and Tamaki Drive – Parking occupancy and turnover surveys were completed in December. Another set of surveys are planned of AT assets in the town centre and along Tamaki Drive during first quarter 2014. This is to assist with the corridor management plan.

Howick

122.   Howick Village parking study – A Howick Village parking study has been drafted and is being finalised.

 

123.   Halfmoon Bay Car Park – Implementation of a 14 hour parking restriction with some dedicated carpool bays was completed in Dec 2013.

Kaipatiki

124.   Mirovale Place, Sunnynook  - Installed a P120 parking restriction in November.

 

125.   Link Drive, Wairau Valley  - Installed a P120 parking restriction in December.

Manurewa–Papakura

126.   Papakura – AT obtained consent for the continuation (eighteen months) of the temporary Park and Ride site.

Albert-Eden

127.   Dominion Rd project – Parking occupancy surveys were completed for Dominion Road in November 2013.

 

128.   Miro Street and Tawera Rd, Greenlane – Consultation on a proposal to install P120 time restriction was completed in October 2013 with positive feedback.

 

129.   Veronica Street, New Lynn – A new P120 time restriction hs been installed.

Henderson–Massey

130.   Henderson Town centre review – Consultation was undertaken in November 2013 for a new P90 parking zone, for Great North Road, Henderson and adjacent side streets along the main arterial. Results of the consultation will be presented to the Henderson-Massey local board in February 2014.


 

Attachments

No.

Title

Page

aView

AT activities, broken down by Local Board

33

bView

Decisions of the Transport Co-ordinating Committee, by Board

63

cView

Report against local board advocacy issues (replaces the previous reports against the Local Board Plan and Local Board Agreement)

65

dView

Report on the status of the Board’s projects under the Local Board Transport Capital Fund

67

     

Signatories

Authors

Various Auckland Transport authors

Authorisers

Jonathan Anyon, Elected Member Relationship Team Manager

Glenn Boyd - Relationship Manager Henderson-Massey, Waitakere Ranges, Whau

 


Henderson-Massey Local Board

20 March 2014

 

 































Henderson-Massey Local Board

20 March 2014

 

 



Henderson-Massey Local Board

20 March 2014

 

 



Henderson-Massey Local Board

20 March 2014

 

 



Henderson-Massey Local Board

20 March 2014

 

 

Auckland Transport Update Report – Henderson-Massey Local Board

 

File No.: CP2014/03232

 

  

 

Executive Summary

The purpose of the report is to respond to Local Board requests on transport-related matters and to provide information to Elected Members about Auckland Transport activities in their Board area.

 

 

Recommendation/s

That the Henderson-Massey Local Board:

a)    Receives the Auckland Transport Report for the Henderson-Massey Local Board be received.

b)    Determines which bus shelters they would like to include in a programme of glass artwork to be forwarded to Auckland Transport.

 

 

Discussion

INFORMATION REPORTS

 

APRIL LOCAL BOARD WORKSHOPS – PRE-ENGAGEMENT ON TRANSPORT LTP

1.    Auckland Transport is scheduling workshops for Councillors and Local Board Members for the second and third weeks of April 2014.  The workshops aim to gain early feedback and options for Transport as input into Auckland Council’s 2015-25 Long Term Plan (LTP) and the Regional Land Transport Plan (RLTP). 

 

2.    Formal consultation on the Transport component of Auckland Council’s Long Term Plan, and on Auckland Transport’s Regional Land Transport Programme, will take place in January and February 2015.

 

PROPOSED LINCOLN ROAD CORRIDOR IMPROVEMENTS PROJECT

3.    The Public consultation feedback period  finished on 7 February 2014. 161 submissions were received on the proposal. Auckland Transport is presently reviewing all the feedback. 

 

 

TE ATATU CORRIDOR IMPROVEMENT PROJECT – MARCH 2014

4.    Auckland Council Property Limited (ACPL) is undertaking the acquisition phase of the Te Atatu Corridor Improvement Project.

 

5.    At this stage ACPL has been working on this project for over 2 years and can report that:

 

6% of the owners are still working with ACPL to agree reinstatement or financial compensation

 

5% of the owners are at the verbal agreement stage, having resolved both reinstatement work and financial compensation, but have yet to sign agreements

 

89% of the owners have signed acquisition agreements or have already settled

 

6.    Events since the last update in November 2013: For the owners yet to sign agreements, the serving of Section 23 notices pursuant to the Public Works Act has begun with 3 currently served and a further 6 to be served within the next two weeks.

RESPONSES AND PROGRESS REPORTS  

 

 

ANTISOCIAL USE OF CARS AND FUTURE PLANNING MIHINI ROAD, RANUI

7.    A request has come through to Auckland Transport to address the issues of antisocial use of cars in Mihini Road, Henderson.

 

UPDATE

8.    Auckland Transport is investigating a short term solution that will empower the Police to undertake enforcement while Auckland Transport and the Police investigate suitable pilot scheme (surveillance cameras) to address the bigger problem of antisocial use of vehicles in the Henderson/Massey Local Board area, which includes Mihini Road.

 

9.    Auckland Transport Traffic Bylaw 2012 – Clause 15 Light motor vehicle restrictions, allows Police to deal with anti-social behaviour associated with car users doing this sort of activity.  This clause allows for cars that are not visiting specific addresses on a road, to be prohibited from a road during the hours of 9pm and 4am. 

 

10.  Auckland Transport understand that the Police will find this to be a useful tool in dealing with problems of this sort.  The Concourse and Mihini Road look like they would be a appropriate roads for this bylaw restriction to be used because there are few venues along this road which would be having customers arriving during the prohibited times.  It is harder to use this power if there are late night venues on a street and car drivers can claim to have been visiting these premises. 

 

11.  At present our Road Corridor Operations is submitting a report to the Traffic Control Committee for approval to enforce this bylaw for “The Concourse and Mihini Road.

 

 

PROPOSED P90 PARKING ZONE FOR HENDERSON TOWN CENTRE

12.  Auckland Transport has been working with the Henderson Retail Business Association and the previous Henderson/Massey Local Board, on ways to improve parking restrictions throughout the Henderson Town Centre. The existing short stay parking restrictions of 30-minutes or less, do not provide sufficient time to accommodate the main retail and commercial activities. In addition, the current range of parking restrictions can be confusing and, result in an excessive number of parking signs in a relatively small area.

 

13.  In order to address this issue Auckland Transport and the Henderson/Massey Local Board have developed a proposal to install a ninety minute parking zone throughout the main town Centre.

 

14.  This proposal involves changing many of the existing on-street parking restrictions, which will reduce the number of signs and different restrictions. The type of signage used to describe parking restrictions will also change. The restriction would operate from 8 am to 6 pm Monday to Sunday. The total number of parking spaces will remain the same.

 

15.  The P90 parking zone will be demarcated by “P90 Zone begins” at the entry points to the zone and “P90 Zone ends” at exit points from the zone. “P90 zone” repeater signs will be installed at 200 metre (or less) intervals. Other varying restrictions within the zone will be indicated by signs and road markings.

 

16.  The proposal will reduce the total number of parking signs and should improve how the streetscape looks and feels, reduce footpath clutter, help pedestrian flow and provide a safer walking environment.

 

17.  The proposal involves changes to the existing parking restrictions in the following areas-

 

a.   Great North Road P5, P15, P30 and P60 restrictions will change to P90 parking zone restrictions.

 

b.   Waitakere Lane - P30 will change to P90 parking zone restrictions.

 

c.   Trading Place P30 and P60 restrictions will change to P90 parking zone restrictions.

 

d.   Ratanui Street P15, P30 and P120 restrictions will change to P90 parking zone restrictions

 

e.   Alderman Drive - P60 and P120 restrictions will change to P90 parking zone restrictions.

 

f.    Railside Ave - P30 restrictions will change to P90 parking zone restrictions.

 

g.   Edsel Street P30 restrictions will change to P90 parking zone restrictions.

 

h.   Catherine Street P30 restrictions and unrestricted spaces will change to P90 parking zone restrictions.

 

i.    Pioneer Street P30, P120 restrictions and unrestricted spaces will change to P90 parking zone restrictions.

 

j.    Existing Mobility Parking, Bus Stops, Taxi Stand, Loading Zones, P5 pick up and drop off areas, Police Parking and “No Stopping at All-time restrictions (yellow lines) will be retained.

 

18.  Before making a decision, Auckland Transport is consulting with affected parties and is seeking comments from the Local Board on what is being proposed.

 

GALLONY AVE BUS STOP REMOVAL

19.  As a part of a wider Auckland Transport’s Bus stops improvement programme the two bus stops outside 2 Gallony Avenue and 9 Gallony Avenue have been made redundant as they are no longer required.

 

20.  Auckland Transport is proposing to remove the existing bus stop from outside 2 and 9 Gallony Avenue, Massey and suggests the following changes:

·       Removal of the existing bus stop outside 2 Gallony Ave, Massey and installation of a parking bay for a maximum up to three cars. This parking space will be unrestricted i.e. no time limit and will be marked the same as the other existing markings to match the current situation of the parking on the road.

·      Removal of the existing bus stop outside 9 Gallony, Ave and installation of no parking broken yellow lines there. As there is not enough room for the provision of a dedicated parking space between the driveways of 9 & 11 Gallony, Avenue, the no parking yellow broken lines are required to ensure that there is no parking and no blockage to vehicle entrances there.

 

21.  These changes are planned to be implemented in early to mid-2014. The Transport Portfolio Leads have been briefed on what is proposed.

 

KINTARA DRIVE - KEA CROSSING

22.  Auckland Transport has received a request form Colwill School to improve pedestrian safety on Kintara Drive.

 

23.  Auckland Transport is proposing to install a Kea Crossing on Kintara Drive as shown on the attached drawing. (Attachment A)

 

24.  Kintara Drive is a local road, and is predominantly a residential area. Colwill School and Colwill Kindergarten are both located on Kintara Drive.

 

25.  Auckland Transport’s proposal is to install a Kea Crossing on Kintara Drive. In order to achieve sufficient visibility for pedestrians crossing the road, NSAAT lines are also proposed as per the attached drawing.

 

26.  The proposal of installing a Kea Crossing on Kintara Drive would help pedestrians especially school children and parents cross Kintara Drive safely during Kea Crossing operational periods. The proposed NSAAT lines indicated on the drawing attached would also help pedestrians cross roads safely outside the Kea Crossing operational periods. Therefore, the installation of a Kea Crossing as per attached drawing would improve pedestrian safety on Kintara Drive.

 

27.  22 consultation letters were sent to the affected residents, property owners, Colwill School and Colwill Kindergarten on Kintara Drive in January 2014.   Consultation with the affected residents and property owners on Kintara Drive has now been completed.

 

28.  The following responses were received:

·    4 supported the proposal

·    Colwill School and Colwill Kindergarten supported the proposal

·    1 with no reference

·    1 objected to the proposal. This is because the proposed location of a Kea Crossing is close to the resident’s property, and the resident is not happy for the on-street car parks to be removed outside his property. The current on-street car parks outside his property are time-restricted, with no parking from 8-9am and 2:30-3:30pm. The resident requested to keep current parking restrictions, and not remove the car parks completely. The resident was advised that this crossing facility will also be used outside the Kea Crossing operational periods, NSAAT lines are required to keep sufficient sight distance. The current proposal is according to the minimum requirement to keep sufficient sight distance. The resident has now accepted Auckland Transport’s explanation.

 

29.  The Transport portfolio Leads have been briefed on what is proposed.

 

INSTALLATION OF DRIVER FEEDBACK SIGN ON AMESBURY RISE/SUMMERLAND DRIVE, BRUCE MCLAREN ROAD, CRAIBURN STREET/WAITEMATA DRIVE and GLEN ROAD

30.  Auckland Transport has received a request from the Local Board to assess a number of streets in the Henderson Massey area for the installation of electronic Driver Feedback signs which display the speed of approaching vehicles.

 

31.  The Driver Feedback sign is solar powered and does not create any noise during its operation.  It is intended that the driver feedback sign will be rotated regularly in other streets within the Henderson Massey area where speeding issues have been identified or reported.  The proposed site is part of the rotational programme and it is envisaged that the sign will be installed sometime in the next 12-15 months for a minimum period of 6 months.  Plans are attached to this report of the allocated areas where the signs will be installed.

 

32.  The Transport portfolio Leads have been briefed on what is proposed.

 

 

LOCAL BOARD TRANSPORT FUND APPLICATIONS

 

Bus Stop Glass Artwork

33.  The Local Board has recently been provided a list of bus shelters in the Henderson/Massey Local Board area.  The Local Board now needs to determine which of these sites they would like to progress with the installation of artwork for the glass.  When this is determined Auckland Transport PT Operations team will work with the Local Board and engage a local artist to design appropriate artwork with a local flavour.  The approximate order of cost per shelter is $2,000.

 

34.  Attached to this report is the updated spreadsheet on the financials for the Local Boards information.

 

ISSUES PENDING

Subject Name

Description

Date Requested

Request Due Date

Summerland Drive Roading Issues

Request Auckland Transport to look at the speeding issues and the increase of heavy vehicles on Summerland Drive.

 February 2014

April 2014

Dust Nuisance Swanson Road

Request Auckland Transport to look at the dust nuisance between 598 and 622 Swanson Road.

 January 2014

April 2014

Taikata Road Crossing Request

Request Auckland Transport to look at the safety issues when crossing Taikata Road and what options are available to mitigate the safety concerns.

February 2014

April 2014

 

WORKSHOPS UNDERTAKEN WITH THE LOCAL BOARD

Subject Name

 Workshop Date

Description

 

Railside Avenue, Henderson - Proposed bus stop changes

6 March 2014

Auckland Transport presented the outcome of the consultation on the proposed bus stop changes.  The Local Board gave feedback on the proposal.  The Local Board comments will be investigated and then Auckland Transport will come back to a further workshop, with the final concept for the Local Board’s information.

 

Te Atatu Bus Interchange Project

6 March 2014

Auckland Transport spoke to the letter that was provided to the Local Board and residences, on the update to the Te Atatu Road/SH16 bus interchange project and outlined the progress made since the last update letter was issued in November.  At present it is expected that the option evaluation will be completed and a decision made on the preferred option by late April to early May 2014. When this decision has been made Auckland Transport will present to the Local Board and inform residents of the outcome.

 

Bordeaux Parade

6 March 2014

Auckland Transport were invited to answer questions about the traffic impact on Bordeaux Parade. 

 

Waitemata Drive – Future Planned Works

6 March 2014

Auckland Transport was requested to look at what future plans there are for a road connect on Waitemata Drive West.

 

 

 

ISSUES CLOSED

Subject Name

Description

Subject Requested Date

Subject Closed Date

Beach Road Calming Measures

As Beach Road is on a public bus route, speed cushions are being proposed as the traffic calming device rather than speed humps.  In conjunction with the speed cushions, there will be new road markings, signage and a lighting upgrade. The4s changes will enhance delineation and improve safety.   It is expected that these improvements can be implemented by July 2014. 

September 2013

March 2014

Speeding Issues On Kereru Street, Henderson

Kereru Street is not eligible for immediate changes but Auckland Transport have added it to its ranked list of sites to await future speed calming treatment. This programme of work is subject to an annual reprioritisation of projects for delivery within the allocated resources and funding.  Once the carriageway maintenance works have been completed Auckland Transport will assess the bend for an advisory speed limit and it is expected that the advisory curve warning signage will be installed early in 2014.

November 2013

March 2014

Merchant Avenue - Speed Humps Installation

Merchant Avenue is a short road with two relatively smooth bends. The road slopes downhill from both ends towards 14 Merchant Avenue. The sloping nature of the road seems to encourage some motorists to speed. Taking all of the factors into account, Auckland Transport is proposing to install speed humps on Merchant Avenue to slow the traffic and improve road safety. During the consultation process, Auckland Transport sent out 29 consultation letters to residents. 24 supported the proposal and two had no preference. In the written responses, most of the residents on Merchant Avenue fully supported the installation of the speed humps on Merchant Avenue. The Local Board Transport Leads have seen the proposal and have been briefed on what is proposed.

November 2013

March 2014

Ebony Place, Massey Truck Noise Issues

Auckland Transport and Auckland Council have been working on this matter together and have decided this particular enquiry relates to an excessive noise issue, which is managed by Auckland Council.  Auckland Council has advised that the customer has replied to their enquiries for further information and this issue seems to have quietened down for now.

November 2013

March 2014

 

 

 

 

Attachments

No.

Title

Page

aView

Attachment A

77

     

Signatories

Authors

Owena Schuster Manager (West), Auckland Transport)

Authorisers

Jonathan Anyon, Elected Member Relationship Team Manager

Glenn Boyd - Relationship Manager Henderson-Massey, Waitakere Ranges, Whau

 


Henderson-Massey Local Board

20 March 2014

 

 








Henderson-Massey Local Board

20 March 2014

 

 

Local & Sports Parks West Draft 2014/2015 Capital Works Programme

 

File No.: CP2014/01954

 

  

 

Purpose

1.       To seek approval from the Henderson-Massey Local Board for the draft capital work programme proposed by Local & Sports Parks West (LSPW) for the 2014/2015 financial year.

Executive Summary

2.       The Local Boards Parks capital work budget for 2014/2015 is $3,731,662.  This includes $179,000 provided in regional funding as part of the Sports Field Capacity Development programme. The programme has been developed from information received through asset condition auditing, requests from the Local Board and from residents through the Councils service request system.

 

Recommendation/s

That the Henderson-Massey Local Board:

a)      Approves the Local & Sports Parks West Draft 2014/2015 Capital Works Programme.

 

Discussion

3.       LSPW manages a range of assets on local parks and sports parks. The programme includes the renewal of existing assets and development of new assets.  These include sport fields, carparks, playgrounds, amenity lighting, park furniture and signage, changing room and toilet facilities, walkways and footbridges, stormwater and drainage requirements.  Provision is made for the programme in the Long Term Plan.

4.       The Henderson-Massey Local Board Local and Sports Park capital budget for 2014/2015 financial year is $3,731,662 including $179,000 provided from the Sports Field Capacity Development fund to design an artificial sports field facility at Massey Domain and to design the upgrade of the no 2 sports field at Ranui Domain including lighting (construction to be undertaken during the 2015/2016 FY).

5.       $32,067 of deferrals has been identified in the 2013/2014 financial year.  This work is now planned to be undertaken during the 2014/2015 financial year.

6.       LSPW is seeking Local Board approval of their capital work programme for the 2014/2015 financial year.  The following are the key projects:

·  Royal Reserve – renewal of no 1 sports field;

·    Te Pai Park – renewal of playground;

·    Te Pai Park – renewal of toilet block;

·    Fred Taylor Park – renewal of no 5 sports field and sports field lighting;

·    Moire Park – renewal of walkways/tracks;

·    Henderson Park – renewal of footbridge;

·    Emerald Valley Park – renewal of playground; and

·    Massey Domain – design of artificial sports field facility and changing room block.

 

7.       The costs shown on the attached programme are estimates only and the actual cost will not be known until the project work is taken through the procurement process.  Adjustments to the programme may be required when the actual costs are identified.  Changes of over $50,000 will be reported to the Local Board for their approval. 

 

Consideration

Local Board Views

8.       A workshop was held on 25 February 2014 with the Henderson-Massey Local Board to discuss the proposed programme.

Maori Impact Statement

9.       The work programme will ensure that facilities continue to be well maintained community assets benefiting the local community, including Maori.

Implementation Issues

10.     There are no known implementation issues arising from this programme.

 

Attachments

There are no attachments for this report.     

Signatories

Authors

Helen Biffin - Team Leader Parks Liaison and Development

Authorisers

Ian Maxwell - Manager Parks, Sports & Recreation

Glenn Boyd - Relationship Manager Henderson-Massey, Waitakere Ranges, Whau

 


Henderson-Massey Local Board

20 March 2014

 

 

Auckland Council Property Limited Local Board Six-Monthly Update
1 July to 31 December 2013

 

File No.: CP2014/04327

 

  

 

Purpose

The purpose of this report is to update the Henderson-Massey Local Board of the activities of Auckland Council Property Limited (ACPL) for the six months 1 July to 31 December 2013.

Executive Summary

1.         ACPL’s goal is to be recognised as a “centre of excellence” that brings commercial expertise and provides value for money to Auckland Council across a discrete property portfolio valued at approximately $1 billion.  ACPL provides commercial expertise in property management, the buying, selling of properties and by and strategically developing council assets.   As a substantive CCO with a commercial focus ACPL provides crucial support to a council organisation that efficiently and effectively achieves social, economic, cultural and environmental outcomes for Auckland.

2.         In order to achieve our goal and meet the expectations of the Mayor and the council, ACPL will work towards seven key outcomes over the next three years. These are:

·    Properties managed for the council and Auckland Transport (AT) are fit for purpose and net returns optimised.

·    Place-shaping partnerships are effectively planned and managed to project completion and in accordance with Auckland Plan objectives.

·    ACPL identifies housing opportunities and collaborates with partners to deliver exemplar housing developments, particularly in the more affordable spectrum of the market.

·    Council business interests are managed to protect long term value and achieve budgeted net return. 

·    Property acquisitions are undertaken in a commercially robust manner and in accordance with the council and AT agreed requirements and relevant legislation.

·    Council and AT property disposals are undertaken in a commercially robust manner.

·    The council is provided with a commercial perspective on planning and development initiatives to support effective implementation of those initiatives.

3.         A summary of ACPL activities specific to the Henderson-Massey Local Board is outlined in the Discussion section of this report with supporting detail included in Attachments B, C, and D.

 

Recommendation/s

That the Henderson-Massey Local Board:

a)      Receives the Auckland Council Property Limited Local Board Six-Monthly Update Report 1 July to 31 December 2013.

 

 


Discussion

Principles for working together

4.         ACPL’s Local Board Engagement Plan (LBEP) states that a successful working relationship between local boards and ACPL is founded on the following high-level principles which will guide our engagement with the local boards:

·   a shared understanding of and mutual respect for the roles, responsibilities and decision-making authority of local boards, the governing body and ACPL; 

·   transparent and timely communication with no surprises;

·   understanding and acknowledgment of shared responsibilities between the parties;

·   a commitment to a timely response to and resolution of issues raised by local board members;

·   a commitment to early inclusion in the planning and decision making process where issues have a specific relevance to a Local Board;

·   a commitment to flexibility in terms of engagement, recognising differing levels of interest and local relevance across the Auckland region.

 

5.         ACPL’s commitment to the local boards is outlined in detail in our LBEP, which is attached as Attachment A for reference. 

Workshops and Meetings

6.         A schedule of Henderson-Massey Local Board workshops and meetings attended by ACPL representatives from July to December 2013 is attached as Attachment B. The list includes property specific meetings and workshops relating to general property management and the ongoing portfolio Rationalisation Process.

Property Portfolio Management

7.         ACPL manages all non-service properties. These are properties not immediately required for service delivery or infrastructure development that are owned by Auckland Council or Auckland Transport. The current property portfolio includes industrial sites and buildings, retail tenancies, cafés, restaurants, offices and a substantial portfolio of residential properties. ACPL’s improved property knowledge and understanding has enabled it to optimise revenue streams and identify future opportunities. 

8.         The property portfolio has continued to grow during the last six-months and now totals 1095 properties. Rent arrears and vacancies were effectively managed throughout the period. During Q1 the average monthly collectable arrears rate and vacancies rate were respectively 1.35% and 2.93%. ACPL’s return on the property portfolio for the quarter ending 30 September 2013 provides the shareholder a net surplus above YTD budget of $2m.

9.         Property portfolio information detailing current ACPL managed commercial and residential property within the Henderson-Massey Local Board area is attached at Attachment C of this report. The report includes each property’s classification or reason for retention along with additional notes to identify the nature of the property, such as a café within a library, or a residential property with tenancy in place. It has also been updated to show properties for which council directs that the operating budget and lease revenue will be included in local board budgets from July 2014.

10.       A report indicating portfolio movement in the local board area is attached as Attachment D. The report details all new acquisitions including the reason for acquisition, any transfers and the reason for transfer, and any disposals.


Portfolio Review and Rationalisation

11.       ACPL is required to undertake ongoing rationalisation of the council’s non-service assets. This includes identifying properties from within council’s portfolio that may be suitable for potential sale and development if appropriate. ACPL has a particular focus on achieving housing outcomes. Identifying potential sale properties contributes to Auckland Plan outcomes by providing the council with an efficient use of capital and prioritisation of funds to achieve its activities and projects. ACPL and Auckland Council’s Property Department work collaboratively on a comprehensive review process to identify such properties.

12.       Once identified as a potential sale candidate a property is taken through a multi-stage Rationalisation Process. The agreed process includes engagement with; council, CCOs, local board and mana whenua. This is followed by ACPL Board approval, engagement with local ward and the Independent Maori Statutory Board and finally a governing body decision. A detailed process flowchart is provided as Attachment E.

13.       Council is budgeting to receive proceeds from the sale of surplus properties of $80 million in 2012/2013 and $58 million in 2013/2014. The financial implication of not achieving these budgets would be higher debt and therefore higher interest costs compared to budget. 

14.       Properties currently under review for future use opportunities via the Rationalisation Process in the Henderson-Massey area are listed below. The list includes any properties that may have recently been approved for sale or development and sale by the governing body. Further details are included in Attachment C.

PROPERTY

DETAILS

23 – 33 Henderson Valley Road, Henderson

Part of Wilsher village, ACPL looking at housing development options here.

2 – 4 Henderson Valley Road, Henderson : Central One

Part section of land at Central One. A Waitakere Properties Limited legacy development that ACPL is now progressing. The mixed use development incorporates commercial and possible residential end uses.

 

Place Shaping and Housing Initiatives

15.       ACPL is contributing commercial input into around 40 council-driven place-shaping and housing initiatives region wide. Involvement extends from provision of initial feasibility advice through to implementation, with projects ranging in size from $400k to in excess of $100million.

16.       A high level update on place-shaping and housing initiative activities in the Henderson-Massey area is outlined in points below.

17.       Waitakere Central (Transit Oriented Development):  This is a Waitakere Properties Limited legacy development that ACPL is now progressing. The mixed use development incorporates commercial and possible residential end uses. Confidential minutes from a Waitakere City Council meeting set out approval for this development along with a request to keep relevant stakeholders updated. ACPL has broached the opportunity for developing all vacant land with several developers. Interest has been expressed in multi-level mixed use development for the site. We anticipate undertaking an RFX process around mid-2014. Sensitivities exist relating to car-parking. ACPL is investigating the viability of a car-parking structure on top of current parking land as a means of resolving this consideration.

 

18.       Wilsher Village Site: This 1.5 hectare site is partially occupied by 34 Housing for the Elderly units. The site is strategically located in Henderson Valley Road and has been identified as suitable for redevelopment. The Request for Proposals closed in October 2013. ACPL is progressing negotiations with developers.

 

Acquisitions

19.       ACPL continues to support Council and Auckland Transport programmes and projects by negotiating required property acquisitions. All such acquisitions are funded through approved Council or Auckland Transport budgets. We also provide advice to assist with budgets, business cases and strategy to support an acquisition.

20.       A total of 54 property purchases to the value of $8.9m were completed during Q1. The number of acquisitions under active negotiations at the end of Q1 was 300 (253 AT and 47 AC).

21.       Recent council acquisitions have included;

-     meeting open space requirements, particularly for subdivisions

-     City Transformation projects

-     Heritage projects

-     Storm water projects.

22.       Current acquisitions programmes for AT include;

-     AMETI (Auckland Manukau Eastern Tamaki Initiative)

-     CRL (City Rail Link)

-     Te Atatu Road, Te Atatu road widening

-     Dominion Road, Mt Eden road widening.

23.       All properties were purchased within the valuation threshold agreed with Auckland Council and Auckland Transport.

24.       Due to commercial sensitivities any Henderson-Massey Local Board specific acquisitions detail will be provided direct to the local board by the Auckland Council or AT project owner.

Business Interests

25.       ACPL manages eight business interests region wide on council’s behalf. This comprises two forestry enterprises, two landfills and four quarries. There are currently no ACPL managed business interests in the Henderson-Massey Local Board area.

Consideration

Local Board Views

26.       This report is for the Henderson-Massey Local Board’s information and seeks the views of the Local Board.

Maori Impact Statement

27.       During the past six months ACPL has further developed our Maori engagement initiatives. Our enhanced process engages with the 19 key mana whenua groups in the Tamaki region on three fronts: identifying cultural significance concerns regarding disposal properties, flagging commercial interests and development partnering discussions. ACPL also engages with relevant mana whenua in respect of development outcomes for ACPL lead projects. ACPL has additionally undertaken to be part of council’s Maori Responsiveness Plan pilot programme. The project’s key output will be an operational document outlining how ACPL will contribute to council’s strategic and operational commitments to Maori. The Current State Assessment phase of this project has been completed and we are now in the Improvement Planning phase. ACPL will advise the Henderson-Massey Local Board as appropriate of any specific discussions that arise in the local board’s area.

General

28.       This report is intended to help ACPL meet its statutory obligations under the Local Government Act 2002. The relevant sections of the Local Government Act 2002 are noted below for information.

29.       As provided in section 59(1) of the Local Government Act 2002, the principal objective of a CCO is to:

(a)    achieve the objectives of its shareholders, both commercial and non-commercial, as specified in the statement of intent; and

(b)    be a good employer; and

(c)    exhibit a sense of social and environmental responsibility by having regard to the interests of the community in which it operates and by endeavoring to accommodate or encourage these when able to do so; and

(d)   the CCO is a council-controlled trading organisation, conduct its affairs in accordance with sound business practice.

30.       As provided in clause 1 of Schedule 8 of the Local Government Act 2002, the purpose of the SOI is to:

·    state publicly the activities and intentions of a CCO for the year and the objectives to which  those activities will contribute;

·    provide an opportunity for shareholders to influence the direction of the organisation; and

·    provide a basis for the accountability of the directors to their shareholders for the performance of the organisation.

Implementation Issues

31.      There are no implementation issues.

 

 

 

Attachments

No.

Title

Page

aView

ACPL DRAFT Local Board Engagement Plan

93

bView

Schedule of Meetings and Workshops

109

cView

Properties Managed by ACPL in the Local Board area

111

dView

Property movement in the Local Board area

113

eView

Rationalisation Process Flowchart

115

     

Signatories

Authors

Caitlin Borgfeldt     Local Board Liaison

Authorisers

David Rankin    Chief Executive

Glenn Boyd - Relationship Manager Henderson-Massey, Waitakere Ranges, Whau

 


Henderson-Massey Local Board

20 March 2014

 

 

















Henderson-Massey Local Board

20 March 2014

 

 


Henderson-Massey Local Board

20 March 2014

 

 


Henderson-Massey Local Board

20 March 2014

 

 


Henderson-Massey Local Board

20 March 2014

 

 



Henderson-Massey Local Board

20 March 2014

 

 



Henderson-Massey Local Board

20 March 2014

 

 

Infrastructure and Environmental Services Update Report

 

File No.: CP2014/00651

 

  

 

Purpose

1.       To inform the local board about the activities of the Infrastructure and Environmental Services (I&ES) department during the period from December 2013 to January 2014. This includes both local board based and regional activities undertaken by the three units of I&ES – Environmental Services, Solid Waste and Stormwater.

2.       This report also tracks the delivery and expenditure of environmental budget lines from the 2013/2014 Local Board Agreement (LBA), as assigned to I&ES.

Executive Summary

3.       I&ES delivers on the Auckland Plan and local board plans through the provision of environment and sustainability programmes, regional waste and stormwater services, as well as the maintenance and enhancement of Auckland's natural environment.

4.       This report has been written to inform the local board about the delivery of activities and work programmes by I&ES. A number of these regional activities have a distinct local involvement and impact and are detailed in the attachments to this report.

 

Recommendation

That the Henderson-Massey Local Board:

a)      Notes the information in the Infrastructure and Environmental Services update report.

 

Discussion

5.       This report and attachments specifically detail the activities delivered by the three units of I&ES within the local board area which support and contribute to the following local board plan priorities and initiatives:

Priority:

Initiatives:

Caring about our environment

·    Ongoing funding for development of Project Twin Streams networks to encourage communities and groups to take ownership of their local environment

·    Maintain Project Twin Streams streams, tracks, walkways and cycleways

·    Continue to partner with Ecomatters Trust (for example Eco Day and the Sustainable Living Centre)

·    Continue to partner with the Keep Waitakere Beautiful Trust (including Trees for Babies and Neat Streets programmes)

·   Examine further opportunities to expand the Green Network

6.    The local board is supporting the delivery of local environmental programmes through its budgets as outlined below. Key project highlights and milestones are noted in the table below with additional detail provided in Attachment A.

Budget Line

Projects

Highlights:

Budget

Community environmental services

Ecofest

·    Organisation for the annual Ecofests in the North and West of the region is underway in conjunction with Kaipatiki Project and Ecomatters Trust. The Ecofests will run from mid-March to mid-April in 2014.

$257,724 (across the three western local boards)

Project Twin Streams Capex

Project Twin Streams

·    In November, December 2013 and January 2014, a total of 1,640 volunteers spent 606 volunteer hours working on streams within the Project Twin Stream area.

Henderson Massey Local Board has $867,542.76 (63%of the total budget) for the 13/14 financial year. This amount includes carry overs.

Resource recovery facility

Resource recovery facility

·       A memo outlining progress and next steps was sent to the local board 17 February 2014.

$21,000 ($7,000 from each board)

Septic tank pump out scheme

Septic tank pump outs

·       Septic tanks - Auckland Council’s stormwater operations team is now responsible for the maintenance of the septic tank pump out contract. In January of this year 94 of the total 134 work orders for the triennial pump out were completed. The 40 remaining work orders were rescheduled for a number of reasons, e.g. the septic tank could not be located (owner advised), the property could not be accessed due to weather conditions, or the standard septic tank had been upgraded to a high tech system.

Budget 2013-14: $686,621.00 across all boards (excludes carryover budget of $259,846.72 for the separate data investigation project to start in March/April 2014)

 

7.    Local environmental initiatives are also supported through regional funding. Highlights of our regional activities are noted in the table below with additional detail provided in Attachment B.

Unit

Highlights:

Environmental Services

·    A total of 132 successful applications shared a total of $619,512 of funding from the annual Environmental Initiatives Fund. Funding was approved at the December 2013 meeting of the Environment Climate Change and Natural Heritage Committee.

·    Organised and facilitated a national kauri dieback symposium, attended by 200 people including scientists, policy makers, land managers and community groups.  The symposium was an excellent opportunity to showcase the leadership of scientists and Auckland Council staff in actively managing this disease.

Solid Waste

·    Successful trial of new inorganics collection model in October-November 2013. Over 50% of material collected recycled or reused.

·    $293,878 awarded to 33 different projects through the Waste Minimisation and Innovation Fund in the October funding round.

·    Upcoming trial of organic food waste collection service to be held on the North Shore from March to May 2014.

Stormwater

·    Stormwater projects as described in Attachment C are being progressed within the Henderson-Massey Local Board area. The Smythe Road renewal and Pankhurst Road project are in the construction stage.

Consideration

Local Board Views

8.       This is a report prepared specifically to inform the local board.

Maori Impact Statement

9.       While this report is for information only and does not require any decision making, it is recognised that environmental management, water quality and land management has integral links with the mauri of the environments and concepts of kaitiakitanga.

Implementation Issues

10.     The activities detailed in this report are within budget. Any decisions arising from discussions and planned changes to work programmes will have financial and resourcing implications which will need to be managed.

 

Attachments

No.

Title

Page

aView

Local Infrastructure and Environmental Services Activity

121

bView

Regional Infrastructure and Environmental Services Activity

123

cView

Stormwater Capital Works

125

     

Signatories

Authors

Lucy Hawcroft - Relationship Advisor

Mara Bebich - Senior Relationship & Engagement Advisor

Theresa Pearce - Relationship Advisor

Authorisers

John Dragicevich - Manager Infrastructure and Environmental Services

Glenn Boyd - Relationship Manager Henderson-Massey, Waitakere Ranges, Whau

 



Henderson-Massey Local Board

20 March 2014

 

 


Henderson-Massey Local Board

20 March 2014

 

 


Henderson-Massey Local Board

20 March 2014

 

 


Henderson-Massey Local Board

20 March 2014

 

 


Henderson-Massey Local Board

20 March 2014

 

 














Henderson-Massey Local Board

20 March 2014

 

 

Appointment of additional members to Western Joint Funding Committee

 

File No.: CP2014/04587

 

  

 

Purpose

1.       To appoint a second full member to the Western Joint Funding Committee

Executive Summary

2.       At its 21 November 2013 meeting the Henderson-Massey Local Board appointed Chair Vanessa Neeson as lead and Member Luke Wilson as alternate to the Western Joint Funding Committee.

3.       Staff have since identified that two members from each of the Henderson-Massey, Waitakere Ranges, and Henderson-Massey local boards are required to be appointed as well as an alternate for each board.

4.       A second appointee is required from the Henderson-Massey Local Board for the Western Joint Funding Committee.

 

Recommendation/s

That the Henderson-Massey Local Board:

a)      Appoints a second member to the Western Joint Funding Committee for 2013/ 2014 with appropriate delegated authority to bind the board on decisions relating to the legacy community funding schemes made by the Committee.

 

Attachments

There are no attachments for this report.     

Signatories

Authors

Busola Martins - Local Board Democracy Advisor

Authorisers

Glenn Boyd - Relationship Manager Henderson-Massey, Waitakere Ranges, Whau

 


Henderson-Massey Local Board

20 March 2014

 

 

Confirmation of Workshop Records

 

File No.: CP2014/04579

 

  

 

Purpose

1.       This report presents records of workshops held by the Henderson-Massey Local Board on:

-     11 February 2014

-     18 February 2014 and

-     25 February 2014

Local Board Standing Orders require that workshop records be confirmed at the next meeting of the local board.

 

Recommendation

That the Henderson-Massey Local Board:

a)      Confirms that the records of the workshops held on the following dates and attached are true and correct: 

-     11 February 2014

-     18 February 2014 and

-     25 February 2014

 

Attachments

No.

Title

Page

aView

Workshop record for 11 February 2014

143

bView

Workshop record for 18 February 2014

145

cView

Workshop record for 25 February 2014

147

    

Signatories

Authors

Linda Smith - Senior Local Board Advisor (West)

Authorisers

Glenn Boyd - Relationship Manager Henderson-Massey, Waitakere Ranges, Whau

 


Henderson-Massey Local Board

20 March 2014

 

 

Record of Workshop
Henderson-Massey Local Board

 

Date:               Tuesday, 11 February 2014

Time:               1.00 pm - 5.00 pm

Venue:             Council Chambers, Henderson Service Centre,
6 Henderson Valley Road, Henderson

 

PRESENT:

 

Members:       Vanessa Neeson, JP (Chair)

                        Shane Henderson (Deputy Chair)

                        Brenda Brady, JP

                        Peter Chan, JP

      Will Flavell

      Tracy Kirkley

                        Luke Wilson

                       

Apologies:     Warren Flaunty, QSM

 

 

MATTERS DISCUSSED

 

 

ITEM

PRESENTER

1.0

LOCAL BOARD PLAN AND WORKSHOP PROGRAMME

Discussed the content and format of the Local Board Plan and workshop programme

Linda Smith

2.0

POTENTIAL SPECIAL HOUSING AREAS (SHAS) FOR TRANCHE 3

A confidential briefing by Auckland Councils Housing Project Office to discuss the list of next potential Special Housing Areas (SHAs) for tranche 3 in the local board area and to obtain members feedback on any issues relating to these areas.

David Cleland, Robert Bates, Stephanie Lam, Karen Foster

3.0

WILSHER VILLAGE

Cancelled

Kat Tierney 

4.0

HENDERSON FRAMEWORK IMPLEMENTATION DIRECTION SETTING WITH BECA LTD

The Board discussed a project to identify activities in Henderson metropolitan centre to be included in the Local Board Plan 2014-2017.

Douglas Sadlier & Linda Smith

5.0

FEES AND CHARGES FOR BOOKABLE FACILITIES

The new fees system for community facilities was discussed.

Val Proud

 


Henderson-Massey Local Board

20 March 2014

 

 

Record of Workshop
Henderson-Massey Local Board

 

Date:               Tuesday, 18 February 2014

Time:               1.00 pm - 5.00 pm

Venue:             Council Chamber, Henderson Service Centre, 6 Henderson Valley Road

 

PRESENT:

 

Members:       Vanessa Neeson, JP (Chair)

                        Shane Henderson (Deputy Chair)

                        Brenda Brady, JP

                        Peter Chan, JP (from 2.50 pm)

                        Warren Flaunty, QSM

      Will Flavell (from 3.35 pm)

      Tracy Kirkley

                        Luke Wilson

                       

Apologies:     There were no apologies

 

 

MATTERS DISCUSSED

 

 

ITEM

PRESENTER

1.0

LOCAL BOARD PLAN - UNITARY PLAN

Local Boards will encourage and support their communities to make their own submissions, so that the Hearing Panel can hear the views of the community directly.

Linda Smith

2.0

ROYAL RESERVE DEVELOPMENT

The upgrade of the reserve to cater to planned increased population.

Grant Jennings, Willy Coenradi & (Shane from Thomas Civil)

3.0

OMNIBUS REPORT TO LOCAL BOARDS

A new format of reporting was presented to the Board.

David Rose

4.0

WILSHER VILLAGE

An update was given to the Board on progress on the redevelopment of the Wilsher Village site.

Kat Tierney & Mark Vinall

5.0

MAORI RESPONSIVENESS FRAMEWORK

Council will work to ensure its policies and actions to recognise and protect Maori rights and the interest with Tamaki Makaurau.

Keith Williams & Luella Linaker

 


Henderson-Massey Local Board

20 March 2014

 

 

Record of Workshop
Henderson-Massey Local Board

 

Date:               Tuesday, 25 February 2014

Time:               1.00 pm - 5.00 pm

Venue:             Waitemata Room, Henderson Service Centre, 6 Henderson Valley Road

 

PRESENT:

 

Members:       Vanessa Neeson, JP (Chair)

Shane Henderson (Deputy Chair)

Brenda Brady, JP

Peter Chan, JP

Will Flavell (from 3.40 pm)

Tracy Kirkley (until 3.50 pm)

Luke Wilson

 

Apologies:     Warren Flaunty, QSM

 

 

MATTERS DISCUSSED

 

 

ITEM

PRESENTER

1.0

LOCAL BOARDS FUNDING POLICY

The Board discussed the impact of the proposed local board funding policy on the Henderson-Massey area with council staff.

Andrew Duncan & Aaron Matich

2.0

PARKS 2014/2015 CAPEX PROGRAMME

The Board examined the Parks 2014/2015 capex programme and received answers to their queries form council staff.

Helen Biffin

3.0

PROJECT TWIN STREAMS

Council staff made a presentation on Project Twin Streams.

Gill Thurlow, Mark Maxlow, Juliette Holdgate & Theresa Pearce

4.0

LOCAL BOARD PLAN ENGAGEMENT

Steve Wilcox updated the Board on the Local Board Plan Engagement.

Steve Wilcox

5.0

PSYCHOACTIVE SUBSTANCES

Wendy Kjestrup updated the Board on the work being undertaken on this issue.

Wendy Kjestrup

 


Henderson-Massey Local Board

20 March 2014

 

 

Chair's report

 

File No.: CP2014/04388

 

  

 

Purpose

1.       To provide an opportunity to the Chairperson of Henderson-Massey Local Board to update the board on her activities, projects and issues since Monday, 24 February.

Chairperson’s activities since Monday, 24 February

Monday
3 March

Confirm the names for the Te Atatu Peninsula Community Centre Rooms

Henderson-Massey Safety Plan - progress update

Youth Connections catch-up

Henderson-Massey Local Board Weekly Update

Local Boards Design Champion Network

Tuesday
4 March

Parks portfolio holders

Transport Portfolio briefing

Henderson-Massey Local Board Workshop

 

Wednesday
5 March

iNRF Open Day
(Neurological Rehabilitation Foundation)

Henderson-Massey Local Board Event

Auckland Development Committee Workshop:  Special Housing Areas (SHA) - Tranche 3 - Review of Proposed Tranche 3 Areas

Defining Excellence Awards - Massey University

Thursday
6 March

Local Board Chairs Greenways meeting

Catch-up with Mike Keenan
(HDBI discussion)

Arts Portfolio Catch Up

Henderson-Massey Local Board Business Meeting

Friday
7 March

West Local Boards Cluster Workshop - Community Development - investing in Community Wellbeing

Meeting with Paula Bennett

Henderson Framework Implementation Plan- External Stakeholder Workshop

Saturday
8 March

Dawn Opening 2014 Harbourview Sculpture Trail

 

 

 

Recommendation/s

That the Henderson-Massey Local Board:

a)      Receives the chair’s report.

 

 

Attachments

There are no attachments for this report.     

Signatories

Authors

Busola Martins - Local Board Democracy Advisor

Authorisers

Glenn Boyd - Relationship Manager Henderson-Massey, Waitakere Ranges, Whau