Date:                      

Time:

Meeting Room:

Venue:

 

Thursday 9 June 2016

6.30pm

Waitakere Ranges Local Board Office
39 Glenmall Place
Glen Eden

 

Waitākere Ranges Local Board

 

OPEN MINUTE ITEM ATTACHMENTS

 

 

 

ITEM   TABLE OF CONTENTS                                                                                         PAGE

 

12        Panuku Development Auckland Local Board Six-Monthly Update 1 July to 31 December 2015

A.      Attachment A - correspondence with PDA (7 December 2015)                           3

B.      Attachment B - open space analysis Glen Eden and surrounds                           5

14        Replacement leachate tank Waitakere War Memorial Reserve

A.      Waitakere War Memorial Park tank replacement report                                       7

16        Parks, sport and recreation draft annual work programme financial year 2016-2017

A.      LDI Volunteer Programme WRLB  25-05-16                                                       19



Waitākere Ranges Local Board

09 June 2016

 

 

7 December 2015

 

 

Letitia McColl

Property review team

Panuku Development Auckland

 

Review of land for disposal in Glen Eden – Feedback from Waitakere Ranges Local Board

Panuku Development Auckland has asked the local board for comment on two council owned properties in Glen Eden which are being considered for sale. 

Glen Eden is zoned for growth and is currently regarded as under supplied with open space. A study of the future open space needs of Glen Eden should be undertaken to inform decisions around property disposals.

The local board went on a site visit to the two sites in question and we provide the following feedback:

315a Glengarry Road, Glen Eden – support retaining for park use

The Glengarry Road property should be retained by council for use as a local park. It has great amenity value and is ready for use as a pleasant park in its current state.

The land has a significant street frontage and considerable flat land which could in the future lend itself to a range of recreational and community uses.

The local board asks that the property be transferred to local parks. A modest investment may be looked at in future to enhance the park with signage and furniture and activation. 

Glen Eden overall is undersupplied with open space.

The local board is currently looking at how to improve the local park network in and around Glen Eden.  We need to make better use of our existing parks, and to look for the opportunity to expand the open space network and improve walking and cycling connections.

The land has value as a greenways connection to the nearby Nicholas Reserve, which provides access through to West Coast Road. The local board is working with Auckland Transport to create a shared walking and cycling path along West Coast Road, and this provides a further link.  In future we would look for the opportunity to connect 315a Glengarry Road, though to the reserve on Milan Drive. 

1/16 Sarona Avenue, Glen Eden

In the proposed Auckland Unitary Plan, this part of Glen Eden is zoned for intensification. The Sarona Avenue property is a ten minute walk from Glen Eden train station and town centre, and is located on the edge of the Terrace Housing/Apartment Zone where it transitions to a mixed housing urban zone. See attached map. 

The area is undersupplied with open space, which will become more of an issue as housing density and population increases. 

Glucina Reserve is connected to 1/16 Sarona Avenue by a stream, though the Sarona Ave property is otherwise inaccessible from the park and looks to be neglected. As a first step we would like to see the property and the area around it cleaned up. Rubbish and debris has been dumped into the stream and one side is very overgrown with weeds.

The piece of land in question has some challenges as a park though, given the zoning of the surrounding area, we think it could be retained and planted up as a streamside bush reserve to provide some green space and a wildlife link.

There is a 26 unit Housing New Zealand property at 4100 Great North Road which is connected to Glucina Reserve by a streamside walkway. This is on the opposite side of the stream from 1/16 Sarona Ave. Some consideration should be given as to whether 1/16 Sarona Ave can be made accessible from this walkway to provide a communal space for surrounding residents, including the HNZ tenants. Could it be a community garden for instance?

The property has no street frontage and is on a flood prone area alongside a stream.  On the face of it, the land would have limited market value should council to decide to dispose of it which may beg the question of whether it is worth selling. The local board would like to know the estimated sale value of the property.

Glen Eden zoning in proposed Unitary Plan

Glucina Reserve

 

1/16 Sarona Avenue

 


Waitākere Ranges Local Board

09 June 2016

 

 

Auckland Council Open Space Policy Framework


Waitākere Ranges Local Board

09 June 2016

 

 

Waitākere War Memorial Park tank replacement

 

File No.: CP2016/11851

 

  

 


Purpose

1.       To seek landowner approval from the Waitākere Ranges Local Board to replace the leaking underground leachate storage tank system at the closed landfill at Waitākere War Memorial Park with an above ground storage tank system.

Executive summary

2.       Auckland Council (Council) is the owner and operator of the Waitākere War Memorial Park closed landfill which has a leachate system located at 13 Bethells Road, Waitakere, legally described as Pt Allot 27 Psh of Waipareira SO 36531 (2.0133HA).

3.       This leachate system is part of the closed landfill which sits underneath the Waitakere War Memorial Park. Leachate is the name given to rainwater and groundwater which flows through the rubbish within a closed landfill. It picks up contamination along the way and in this instance drains into an underground storage tank located at the eastern end of the site. This tank is regularly emptied by a mobile tanker, transported to the waste transfer station in Henderson and discharged to the wastewater network.

4.       The leachate collection tank at the Waitākere War Memorial Park is a below ground structure. It has failed and urgently needs to be replaced to prevent leachate entering the adjacent stream.

5.       To temporarily manage this risk a bypass arrangement has been installed. This has only been partially successful and with increased rainfall through the winter months council urgently needs to get a permanent solution in place to prevent direct discharge of leachate to the stream.

6.       Staff have assessed three options for replacement of this tank. Two material options comprising an above ground tank and a below ground tank have been analysed and assessed. A do nothing approach is not acceptable.  A detailed multi-criteria analysis was completed and is attached to this report as attachment A.  The key criteria considered are:

·   Health and safety for council staff and contractors and park users,

·   Environmental performance of the installation options

·   Flexibility and or future proofing of the installation options

·   Impact on stakeholders, and

·   Cost

7.       Particular focus has been paid to safety in design when considering the options.  The Health and Safety at Work Act 2015 requires council to assess the design aspects of its facilities with regard to safety. Under this new legislation council is required to eliminate or mitigate health and safety risks throughout the lifetime of the asset.  A significant risk to be mitigated is the contractor’s exposure to methane in an enclosed space.  Placing the tank above ground eliminates this risk. This risk cannot be eliminated from the below ground option.

8.       Each of the above criteria were weighted with health and safety being given the highest weighting and cost the lowest.

9.       Overall the above ground option can achieve a better level of environmental performance, eliminates a significant risk, allows for more flexibility for future leachate management and finally is significantly more cost effective.

10.     On the basis of this analysis, it is recommended that the above ground option be progressed.

11.     Concerns about the loss of visual amenity value and the potential impact of the above ground tanks on the park have been raised. To address these concerns it is proposed that a landscape architect be engaged to provide options for mitigating this impact. These options may include landscape appropriate tank colouring and native screen planting. Any existing parks management plans and local board preferences would be part of the consideration for this mitigation. Other suggestions from the board to mitigate this impact, including the footprint and height of the existing security fence, landfill cap improvements to support the community aspiration for footpath and community input to the mitigation, will be incorporated in the project.

 


 

Recommendation

That the Waitākere Ranges Local Board:

a)      As landowner, grant approval to replace the existing failed underground leachate storage tank system with an above ground storage tank system, noting that community and local board input will be incorporated into the project to minimise the visual impact.

 

 


Comments

Problem Definition and Proposal

12.     The leachate system, which is part of the closed landfill at the Waitākere War Memorial Park 13 Bethells Road, Waitakere, legally described as Pt Allot 27 Psh of Waipareira SO 36531 (2.0133HA), has failed. Council needs to urgently replace this leachate system to remove the risk of leachate discharging directly to the adjoining stream and the ground around the tank becoming undermined.

13.     Staff have assessed options for replacing this system and recommend the installation of a two tank above ground system for the storage of leachate at Waitākere War Memorial Park. This report seeks landowner approval from the board for this system.

Options

14.     Two options of an above ground and a below ground tank have been assessed.  A detailed multi-criteria analysis is attached to this report as attachment A.  The key criteria considered are:

·   Health and safety for council staff, contractors and park users,

·   Environmental performance of each option

·   Flexibility and or future proofing of the installation options

·   Impact on stakeholders, and

·   Cost

15.     These criteria have been weighted as follows:

Attribute

Weight

Safety

4

Environment

3

Stakeholder disruption / added value

2

Cost

1

Table One: Criteria Weightings for Waitakere Leachate Tank Options

16.     Each of the above criteria were weighted with health and safety being given the highest weighting and cost the lowest. The above ground option scored highest overall. It is recommended that the above ground option be progressed.

17.     A number of scenarios were considered under each option and the impact of these were scored out of 10. With one being the less effective and ten being the most effective. This scoring is described in detailed in attachment A. A summary of the scoring is:

 

Considerations

Option

Safety

Implications for contractors and park users

 

Environment

Potential impacts on surface water, groundwater and soil quality

Stakeholders

Landfill managers, park managers and users, neighbours

Value

Capital and operational expenditure

Combined score

Above ground tank Option

57.3

43.5

31.3

13

145.1

Underground tank option

45.3

39

30

12

 

126.3

 

Table Two: Evaluation of Options for Waitakere Leachate Tank Options

18.     Overall the above ground tank option is recommended because it can achieve a better level of environmental performance, it will allow staff to have immediate visual indicators in the event that the tank or the piped connections leak, and it will offer more flexibility in the future should the need to change the way that leachate is managed or the need to replace the tanks arises.

19.     A significant consideration in analysing these options was health and safety. Due to the nature of the landfill environment the risks associated with the installation and operation of subsurface structures, in particular the presence of landfill gas, are significant. The above ground tank installation is recommended selected as it removes the need for works in a below ground pit as part of the installation and ongoing maintenance of the tank.

20.     Also the above ground design is significantly cheaper than an underground option with initial quotes suggesting that it is around $150,000 cheaper.

21.     In making this recommendation particular focus has been paid to safety in design.  The Health and Safety at Work Act 2015 requires council to assess the design aspects of our facilities with regard to safety. Under this new legislation council is required to eliminate or mitigate health and safety risks throughout the lifetime of the asset.  One of the large risks to contractor safety is exposure to methane in an enclosed space.  Placing the tank above ground eliminates this risk. This risk cannot be eliminated from the below ground option.

22.     It is understood that under the new health and safety legislation there are overlapping Persons in Control of Business or Undertaking (PCBU) responsibilities with respect to this installation.  Board members and council officers would be considered to be the PCBU in this instance and therefore have a primary duty to provide a safe working environment, safe plant, safe systems of work as well as other duties around provision of information training, supervision, facilities and monitoring or health and conditions of work

23.     The below ground option does not eliminate the risk associated with working in an enclosed space with a hazardous atmosphere.  The intent of the legislation is that where overlapping PCBU responsibilities exist, the parties work together to identify the best way to eliminate these risks.  If elimination of risks is not possible then controls should be put in place to minimise them.  The above ground option eliminates these risks.

 

 

Potential Effects and Mitigation

24.     Concerns about a reduction in visual amenity at the site from the preferred option have been raised. It is recognised that there will be some minor visual impact as a result of locating the tanks above ground. However, it is considered that this is minor and not out of context with the setting, where there are existing leachate maintenance structures such as raised manholes.  Furthermore, water tanks, which look very similar in shape and size to the leachate tanks proposed, are a common feature in a rural settlement such as Waitākere, where residents harvest rainwater from their roofs.

25.     A photo montage of what the above ground dual system installation would like without any mitigation is provided in attachment B.

26.     It is proposed that we seek advice from a landscape architect on how to mitigate the minor visual impact of these tanks for example by painting them a colour which blends with the local landscape and by incorporating some screen planting in consultation with the local community. A meeting to discuss this was held with community members on 8 June 2016.

27.     The community were satisfied with the above ground tank option but would like to see some screening of the facility to minimise the loss of visual amenity.  They asked for the tank to be painted a colour that would assist with blending into the background such as green or brown. 

28.     In addition to the visual impact there are a number of beneficial effects associated with the tank replacement, namely that the replacement tank system is expected to improve the performance of the site by minimising losses to leachate to the adjacent stream.  In addition the dual tank system will allow us to complete maintenance of tanks without taking the system offline.

29.     Unlike with an underground tank, the above ground system will enable maintenance contractors to immediately see if there are any leaks from the tank connections rather than these being hidden underground as at present. Maintenance of the tank installation will not require ground breaking works or the need for enclosed space entries.

30.     Following a workshop with the local board some areas for consideration were raised around the preferred option and associated works with the landfill. Staff can incorporate the following into the project:

·   Ensuring the above ground storage does not increase the existing security fence compound footprint.

·   Ensuring the above ground storage does not exceed the height of the existing security fence compound.

·   Supporting the community proposed and funded park footpath by completing cap improvements beneath the footpath out of regional landfill maintenance budgets.

·   Work with the community to identify an appropriate level of screening around the existing security fence compound. A community meeting was held on 8 June 2016 to agree on the value adding features they would like to see.

Consideration

Local board views and implications

31.     The options and recommendation were discussed with the local board at a workshop on 2 June 2016. Staff understand that the board’s key concern is around the loss of visual amenity value at the park.  As described above staff have taken this feedback on board and will address this concern by painting the tank a colour that will blend with the surrounding landscape and with appropriate screen planting following community engagement. In addition staff note the factors around the footprint of the existing site and will ensure these aspects are covered off as described above.

32.     At this same workshop with the local board on 2 June 2016, staff discussed the possibility of reviewing the current performance of the landfill cap on the site with a view to undertaking further improvements to the park surface to offset the loss of amenity value.  Improvements to the performance of the cap would be expected to reduce the volume of leachate generated by this site.  Improvements to the cap would also improve the usability of the park which we consider would be a positive benefit to the community and may off- set concerns around the minor visual impact.  Staff will work with the community to look at options for remediating this in time for the proposed footpath works and most likely in the earthworks season.

Māori impact statement

33.     Due to emergency nature of this work, consultation with Mana Whenua has not been undertaken to date.

34.     As the site is a closed landfill and there is an existing underground tank in the location of the proposed works it is considered unlikely that there are known sites of significance to Mana Whenua located within the vicinity of the works area.

Implementation

35.     Landfill control infrastructure is not formalised through a designation at this site and will be subject to the standard provisions of the Proposed Unitary Plan, the Auckland Regional Plan: Air Land and Water and the Rodney District Plan.  Due to the urgent nature of these works they would be completed under the Emergency Provisions (Sec. 330) of the Resource Management Act and consent applied for retrospectively.

36.     The granting of land owner approval for the proposed works is undertaken as part of the local board’s role and landowner of local parks.  This approval does not bind council in its capacity as a regulatory authority in any way, and any consent given under this agreement is not an approval or consent in its regulatory capacity, and vice versa.  Council will not be liable to any other party if, in its regulatory capacity, council declines or imposes conditions on any consent any party seeks for any purpose associated with this approval.

 

 


Waitākere Ranges Local Board

09 June 2016

 

 

Attachments

No.

Title

Page

a

Options assessment Waitakere War Memorial Park tank replacement

 

b

photo montage of above ground dual system

 

     

Signatories

Authors

Carole Lee: Closed Landfills & Contaminated Land Response Manager

Authorisers

Barry Potter - Director Infrastructure and Environmental Services

Glenn Boyd - Relationship Manager Henderson-Massey, Waitakere Ranges, Whau


Waitākere Ranges Local Board

09 June 2016

 

 

Page_000001


Waitākere Ranges Local Board

09 June 2016

 

 

Page_000002


Waitākere Ranges Local Board

09 June 2016

 

 

Page_000001


Waitākere Ranges Local Board

09 June 2016

 

 

Page_000002 



Waitākere Ranges Local Board

09 June 2016

 

 

Memo                                                        

To:                Waitakere Ranges local board

cc:                

From:            Huw Hill-Male 

 

  Date :            25 May 2016

 

 

Subject:        Waitakere Ranges board LDI Volunteer programme 2016-2017

 

Reserve

Group

Project

Estimated Cost

Perris Road Reserve Walkway

Ahmadiyya Muslim Jama’at New Zealand Inc

Creation of pedestrian walking track, clearing vegetation and plant pests for 1000 lineal metres, followed by replanting.

Environmental weed and deadwood clearance required by contractors.

15,000

Rimutaka Rd Reserve walkway

Local residents

Planting of stream area next to the walking track near 60 Sylvan Valley Road

2500

Glucina Reserve

Local residents

Plant park and streamside areas – two planting dates in 2017 with BBQ for volunteers

6000

Gill Esplanade 2

Rudolph Steiner School

Restore Gill esplanade area to native vegetation

2500

Milan Reserve,

Local residents

Small reserve native bush restoration planting

3000

Miscellaneous

Rubbish clean ups etc

Portaloos, rubbish bags, trapping supplies, traps, bait, Jumbo bins, Rubbish removal, tools

Various reserves

2000

 

 

Total estimated Cost

31,000

N.005301.17