I hereby give notice that an ordinary meeting of the Waitematā Local Board will be held on:

 

Date:

Time:

Meeting Room:

Venue:

 

Tuesday, 21 May 2019

2:00pm

Waitematā Local Board Office
Ground Floor
52 Swanson Street
Auckland

 

Waitematā Local Board

 

OPEN ADDENDUM AGENDA

 

 

 

 

MEMBERSHIP

 

Chairperson

Pippa Coom

 

Deputy Chairperson

Shale Chambers

 

Members

Adriana Avendaño Christie

 

 

Richard Northey, ONZM

 

 

Denise Roche

 

 

Vernon Tava

 

 

Rob Thomas

 

 

(Quorum 4 members)

 

 

 

Liz Clemm

Democracy Advisor - Waitematā

 

17 May 2019

 

Contact Telephone: (09) 353 9654

Email: liz.clemm@aucklandcouncil.govt.nz

Website: www.aucklandcouncil.govt.nz

 

 

 


Waitematā Local Board

21 May 2019

 

 

ITEM   TABLE OF CONTENTS                                                                                         PAGE

    

35        Grey Lynn Park Changing Room and Toilet Facilities                                              5 

 

      


Waitematā Local Board

21 May 2019

 

 

Grey Lynn Park Changing Room and Toilet Facilities

File No.: CP2019/08101

 

  

 

Te take mō te pūrongo

Purpose of the report

1.       To seek approval to construct changing rooms and toilets at Grey Lynn Park, Grey Lynn as per the design and location outlined in this report.

Whakarāpopototanga matua

Executive summary

2.       Grey Lynn Park is a destination park located in Ponsonby. It has a wide range of facilities catering for active and passive recreation. These include three sports fields, two playgrounds, a skate ramp, basketball and tennis courts, an extensive footpath network and two off-leash dog exercise areas.

3.       There is an existing clubroom, which includes toilets and changing rooms that is owned by the Richmond Rovers Rugby League Club. These facilities do not meet the demand for changing rooms required and each winter temporary portacoms are hired to service the fields.

4.       There is also a standalone toilet block at the park that is nearing the end of its life and a condemned athletics building that is no longer in use.

5.       Between April 2015 and May 2019 a range of options for the type of building and the location of a new building have been discussed with multiple stakeholders.

6.       The preferred location (option 3) and design of the building has the following benefits:

·    Eight new toilets (four of which will be open outside of when the changing rooms are being used for organised sport), four new changing rooms and additional onsite storage

·    Improved pedestrian safety – no car movements through the park once removal of the carpark separating fields one and two is complete

·    Improved views through the park and increased passive surveillance

·    Better greenways route alignment once landscaping works are complete

·    The rationalisation of buildings on the park – one new facility will allow the removal of the existing old toilet block and derelict athletics clubrooms. The removal of these buildings is within the scope of this project.

7.       Staff have now completed concept, developed and detailed design for the preferred site.

8.       Construction is still subject to the local board approval (the resolution sought in this report), approval of the growth funded budget from the Finance and Performance Committee (report to committee in July 2019) and granting of the resource consent application which has been lodged.

9.       If these approvals are all forthcoming, the tender process could be completed in August 2019 and the physical works could commence in October 2019.


 

 

Ngā tūtohunga

Recommendation/s

That the Waitematā Local Board:

a)      approve the design and location of the changing rooms and toilets for Grey Lynn Park and request staff proceed to physical works, subject to confirmation of budget allocation and necessary consents.

 

Horopaki

Context

10.     In April 2015, the Grey Lynn Park Development Plan was formally adopted by the local board.  This document had regard to two previous development plans created in 2004 and 2008, as well as a community facility needs analysis. The plan included an optimal location for a future multi-use community facility, based on the best outcome for the wider park.  Development of the plan included Iwi engagement, key stakeholder, council stakeholder and public consultation.

11.     The development plan included a community facility needs analysis undertaken by O’Connor Sinclair consultants. This study identified the current and future building and facility needs of all user groups in the park, reviewed previous park plans and captured the current and future demands of all community and sporting groups with a connection to Grey Lynn Park, through one-to-one interviews.

12.     The development plan identified an optimal location for a possible future multi-use facility, between the existing car park and the south west side of the number one field. This location was identified after reviewing the findings of the community facility needs analysis, and discussions with staff from the Local and Sports Parks and Sport and Recreation Teams.

13.     Benefits of this location included:

•        The rationalisation of buildings on the park – one new facility would allow the removal of several older buildings

•        Improved pedestrian safety – no car movements through the park

•        Improved views through the park and increased passive surveillance

•        Better Greenways route alignment.

14.     Feedback received from the Richmond Rovers Rugby League Club (RRRLC) during consultation on the development plan expressed concerns about the proposed location.  RRRLC requested that if their preferred option to retain a building in its current location could not be achieved, that an alternative location at the end of the main car park, between number one and number two fields, be considered.  

15.     Whilst the RRRLC proposal didn’t meet the recommendations from the community facilities needs analysis, the local board committed to ongoing discussions with RRRLC to see if a solution could be found that was of benefit to the club, the park, all user groups, and local residents.   

16.     It should be noted, at the time of these discussions and adoption of the 2015 development plan, RRRLC were potentially eligible to seek funding through the Multi-Use Facilities Partnership Fund. The availability of this fund was removed prior to the last Auckland Council elections in 2016. 

17.     Following adoption of the 2015 Grey Lynn Park Development Plan and through to February 2018 staff and local board members worked with the RRRLC to agree on a preferred affordable design.  

18.     During this period of engagement, RRRLC requested staff consider construction options that allowed construction of changing room and toilets to be completed but allowed the RRRLC to complete their contribution at a later date. Staff considered this request but it was discounted due to practicality and cost implications. It also created a risk that council would be burdened with a partially completed facility if RRRLC were unable to achieve their required funding. See Attachment A and B for designs presented to RRRLC on 25 January 2018.  

19.     Following both options being presented to RRRLC, the club confirmed that they had no ability to raise the funding required for their contribution to the build or supported a multi-use facility on site. They also reinforced their desire to stay in their current building and undertake their own renovation to the existing clubrooms. RRRLC requested council investigate a location of the changing rooms and toilets as close as possible to the existing clubroom.

Decision-making authority

20.     The local board has the decision-making authority over recreation facilities and initiatives including the specific location, design, build and fit out of new local recreation and sports facilities within budget parameters agreed with the Governing Body and the use of local recreation facilities and initiatives including leasing and changes of use.

Tātaritanga me ngā tohutohu

Analysis and advice

21.     Based on the decision made by the RRRLC, staff prepared two new options for changing and toilet facility only. Option 1 effectively adjoined the southern end of the current RRRLC clubrooms. Option 2 was located at the end of the main car park, between the number one and number two fields the scope for these new options was to still address as many of the benefits identified in the original development plan. 

22.     Following completion of the preliminary site investigation and initial detailed site investigation, the suitability for placement of the changing rooms and toilet at either site raised a number of risks associated with costs to design out site constraints, obtaining resource consent (particularly infringement of side boundary clearance) and constructability.

23.     During an update to RRRLC on 24 August 2018, it was suggested by the club that a third possible location be considered. This location was at the north eastern end of field one and sits between the end of the field and the walkway coming down from Murdoch Road (option 3). 

24.     On 11 September 2018, staff provided an update to the local board with the findings of investigations undertaken and discussion of the third option raised by the RRRLC (see Attachment C for copy of presentation). Based upon the information provided to the board at the workshop, staff were directed to continue investigation of option 3 only as it had considerably lower risks associated with delivery than option 1 or option 2.  

25.     On 29 November 2018, staff met with RRRLC to update on the design for option 3. The club were supportive of the designed provided, however, they re-raised concern that the current car parking adjacent to the existing clubrooms was being removed.

26.     At the 2 April 2019 workshop with the local board, staff included an option to retain three accessible parks near the existing clubroom, however, the local board asked that these not be included as it is contrary to the local board’s direction of not having car parking within Parks and accessible parking requirements would be provided within maintained car park adjacent to field one. 

27.     Staff have now completed concept, developed and detailed design for option 3 and are currently waiting on the decision for resource consent.  

28.     As part of the project to construct the new changing rooms and toilets, the existing toilet block, derelict athletics clubrooms, rock retaining wall and carpark separating fields one and two will be removed. 

29.     The current proposed location (option 3) and design for the changing room and toilets will provide a significant upgrade of amenity at Grey Lynn Park. The final design includes eight toilets, four of which will be open to the public outside of when the changing rooms are being used for organised sport, four changing rooms, referee changing rooms and additional storage rooms.

30.     Crime Prevention Through Environmental Design (CPTED) and safety in design principles have been applied in the design and location of the new facility.

31.     The following Environmentally Sustainable Design considerations have been included:

Electrical

•        All lights are rugged LED fittings for minimal maintenance.

•        Lights are long life usage. meaning less maintenance and replacement and are controlled by occupancy sensors to minimise energy usage.

•        Solar was investigated as an option but found to be uneconomical due to shading, payback on initial investment, and risk of vandalism.

•        The design is future proofed for solar installation with an inverter and cabling for solar panels.

Hydraulics

•        Shower units limit the water use of each shower to a set time frame, reducing the water consumption and heating.

•        The primary hot water source is from instantaneous boilers which only heats the water when it is required.

Passive

•        Natural ventilation is provided.

•        Natural lighting is provided during daylight hours by translucent roofing panels.

32.     Other benefits to the park will include:

•        the rationalisation of buildings on the park – one new facility would allow the removal of the existing old toilet block and derelict athletics clubrooms during landscape works

•        improved pedestrian safety – limited vehicular movements, other than operational maintenance vehicles, emergency services and deliveries to clubrooms, through the park once removal of the carpark separating fields one and two is complete

•        improved views through the park and increased passive surveillance

•        better greenways route alignment once landscaping works are complete.


 

 

Figure 1 – Artist impression of changing room and toilets (preferred option 3)

 


 

Figure 2 – Site plan (preferred option 3)

 

Figure 3 – Detailed planting plan (preferred option 3)

Stakeholder impacts and views

33.     The RRRLC (the domiciled club at Grey Lynn Park) have expressed a preference for option 3 over the other two locations considered.

34.     Their main concern with the design is the loss of car parking immediately adjacent to their existing building.

Ngā whakaaweawe me ngā tirohanga a te rōpū Kaunihera

Council group impacts and views

35.     One impact on other parts of council will be an increase in maintenance and inspection requirements once the new toilet and changing rooms and landscaping are installed. 

36.     The final plans have been discussed and reviewed by the operations team and are in line with the sport field changing room design guidelines

37.     One benefit to the operations team is there is no longer the need to hire temporary changing rooms each winter.

Ngā whakaaweawe ā-rohe me ngā tirohanga a te poari ā-rohe

Local impacts and local board views

Links to strategies, policies and plans

38.     The construction of the changing rooms and toilets at Grey Lynn Park will contribute to achieving three community and sporting related targets in the Auckland Plan:

·    Strategic Direction 5 is to promote individual and community wellbeing through participation and excellence in recreation and sport.

·    Strategic Direction 12 is to plan, deliver and maintain quality infrastructure to make Auckland liveable and resilient.

·    Chapter 5 provides strategic direction on how investment in sport and recreation should be directed to increase participation. It includes a directive to prioritise and optimise sport and recreation facilities, public open space and the capability of sport and recreation organisations.

39.     The upgrade to Grey Lynn Park will support the outcome in the Waitematā Local Board Plan “attractive and versatile public places that meet our community’s needs” through the following objectives and key initiatives:

Objective

Ensure our parks, open spaces and recreation facilities meet the needs of our current and future residents. 

·    Continue to invest in our parks and facilities to ensure they are multi-purpose and can be accessed by a wide range of community groups and users.

Objective

Deliver high-quality facilities that encourage active and healthy lifestyles.

·    Provide more walkways and cycling connections to link our local parks, coastline and recreation facilities, prioritising the Waitematā Greenways Plan.

Tauākī whakaaweawe Māori

Māori impact statement

40.     Auckland Council is committed to meeting its responsibilities under Te Tiriti o Waitangi and its broader legal obligations to Māori. The council recognises these responsibilities are distinct from the Crown’s Treaty obligations and fall within a local government Tāmaki Makaurau context. These commitments are articulated in the council’s key strategic planning documents the Auckland Plan, the 2018-2028 Long-term Plan, the Unitary Plan and Local Board Plans.

41.     Iwi consultation was undertaken through the development of the Grey Lynn Park Development Plan and the Te Aranga Māori Design Principles were applied.

Ngā ritenga ā-pūtea

Financial implications

42.     The cost estimate to construct the proposed toilet and changing rooms, complete landscaping and remove two buildings is estimated to be $1.979 million.

43.     Allocation of growth funding for projects in the financial year 2019/2020 – 2021/2022 three-year work programme will be presented to the Governing Body for approval in June 2019.

Ngā raru tūpono me ngā whakamaurutanga

Risks and mitigations

44.     There are no specific implementation risks anticipated for either option, although typical implementation issues are likely to include:

·        securing resource consent

·        managing impacts of construction works, including noise, construction traffic and other impacts on other park users and adjacent residents

·        managing short term loss of sports field for both sport and events during construction works. Staff are working with Auckland Council Arts, Culture and Event(s) to understand the implication of the construction programme on the Grey Lynn Festival.

45.     Should the local board not approve staff recommendations in this report, it is unlikely the changing rooms and toilets could be built during the 2019/2020 summer.

46.     The final funding is still to be approved by the Finance and Performance (F&P) Committee in June 2019.

Ngā koringa ā-muri

Next steps

47.     Obtain resource consent.

48.     Finance and Performance Committee to approve funding in June 2019

49.     Complete tender documentation

50.     Complete procurement for physical works contractor and mobilise for October 2019 construction commencement.

 

Ngā tāpirihanga

Attachments

No.

Title

Page

a

30 November 2017 Grey Lynn Park Club Changing Rooms, Toilets, Club Rooms - Option 1 (two-storey option)

15

b

30 November 2017 Grey Lynn Park Club Changing Rooms, Toilets, Club Rooms - Option 2 (single-storey option)

17

c

11 September 2018 Grey Lynn Park Club Changing Rooms Concept presentation to Waitematā Local Board

19

d

2 March 2019 Grey Lynn Park Club Changing Rooms Concept

39

      

Ngā kaihaina

Signatories

Authors

Grant Burke - Sports Parks Specialist

Authorisers

Rod Sheridan - General Manager Community Facilities

Simon  Tattersfield - Senior Local Board Advisor - Waitematā

 



Waitematā Local Board

21 May 2019

 

 

PDF Creator


Waitematā Local Board

21 May 2019

 

 

PDF Creator


Waitematā Local Board

21 May 2019

 

 

PDF Creator


Waitematā Local Board

21 May 2019

 

 

PDF Creator


Waitematā Local Board

21 May 2019

 

 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


Waitematā Local Board

21 May 2019

 

 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator