Pukekohe Cemetery Committee workshops

 

OPEN MINUTES

 

 

 

Notes of the Pukekohe Cemetery Committee workshop  held at Franklin the Centre, 12 Massey Ave, Pukekohe on Tuesday, 6 May 2025 at 5.00pm.

 

Te Hunga kua Tae mai | present

 

Chairperson

 

 

Deputy Chairperson

 

 

Members

Member Janie Astle

 

 

Member Alan Cole

 

 

Member Angela Fulljames

 

 

Member Makere Rikka Heke

 

 

Member Sonny Parata

 

 

Member Logan Soole

 

 

Member Harley Wade

 

 

Te Hunga Kāore i Tae Mai | ABSENT

 

 

Member Tearepa Kahi

 

 

 

Member Pare Rauwhero

 

 

 

Member Phyllis Bhana

 

 

 

Te Hunga Āpiti kua Tae mai | ALSO PRESENT

 

 

Carol McKenzie-Rex

 

 

 

 

Mat Glanfield

 

 

 

 

Lucy Stallworthy

 

 

 

 

Raemon Matene

 

 

 

 

Orrin Kapua

 

 

 

 

Matekino Marshall

 

 

 

 


Pukekohe Cemetery Committee workshops

06 May 2025

 

 

 

1          Ngā Tamōtanga | Apologies

 

There were apologies from Tearepa Kahi, Pare Rauwhero and Phyllis Bhana.

 

 

2          Te Whakapuaki i te Whai Pānga | Declaration of Interest

 

There were no declarations of interest.

 

 

5

Pukekohe Cemetery Committee workshop

 

 

Item 1

This workshop was closed to maintain the effective conduct of public affairs through the free and frank expression of opinions by or between or to members or officers or employees of any local authority in the course of their duty

There were no materials.

Item 2

Themes from Engagement

Presenter/s:                  Carol McKenzie-Rex

Purpose:                      Wananga on themes from engagement

Governance role:          Oversight and monitoring

Summary of Discussions

Overview of the Engagement Summary and recommendations in the business meeting report. 

Item 3

Artist selection and design

Presenter/s:                  Mat Glanfield

Purpose:                        Discuss next steps

Governance role:          Oversight and monitoring

Summary of Discussions

Explanation of the process for artist selection and design, how guidance is given to the artist and how the artist is supported.  Need to start with landscape architect with a wide scope, holistic design processes that addresses the things people talked about in engagement – how they want to feel, inclusivity etc.  Noting need for second round of engagement on concept design. 

Item 4

Mana whenua engagement

Presenter/s:                  Carol McKenzie-Rex

Purpose:                       Seeking direction on mana whenua engagement in this project

Governance role:          Provide direction

Summary of discussions

Outline of engagement with mana whenua to date, and approach from iwi who would like to meet to discuss the project.  Matekino Marshall from Ngati Tamaoho Trust spoke to this item and confirmed Tamaoho support for the project and for the committee to make decisions.

Item 5

Oral histories support from Auckland Council

Presenter/s:                  Carol McKenzie-Rex

Purpose                        Oral histories support from Auckland Council

Governance role:          Provide direction

Summary of discussions:

Outline of how Auckland Council Libraries can support oral history interviews.  In principle support for this, and to seek additional budget.  Request for AC libraries staff to come to the committee so committee can better understand how data is used.  Need people from committee to be involved with interviewing.  Suggestion to focus on this towards end of the project.

Item 6

Site Survey

Presenter/s:                  Mat Glanfield

Purpose:                       Update on site survey

Governance role:          Oversight and monitoring

Summary of discussions:

Site survey is underway, weather dependent.

Item 7

Budget and project plan update

Presenter/s:                  Mat Glanfield

Purpose:                       Update project plan and budget

Governance role:          Oversight and monitoring

Summary of discussions:

Overall there is a five week project delay due to delays with engagement and the site survey.  33% underspend to date.

 

 

The workshop closed at 6.40pm